INSP-Final Inspection | 10/10/2002 | 10/10/2002 | 10/10/2002 | A | PASS |
Rick Jackson
|
|
|
|
DOC - Permit Finaled | 10/10/2002 | 10/10/2002 | 10/10/2002 | A | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 10/10/2002 11:30:40 AM
|
INSP-Final Inspection | 10/9/2002 | 10/9/2002 | 10/9/2002 | P | FAIL |
Rick Jackson
|
|
|
dry alarm switch not working
|
Inspection Record Card- Fire | 5/8/2002 | | 5/8/2002 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/7/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 4/5/2002 | | 5/6/2002 | | DONE |
|
|
|
5/6/2002 13:43:23 JWA - activity updated through activity FIRA22 from case FIR02-00157.
|
Sprinkler Plan Check | 4/29/2002 | | 5/6/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2002 | | DONE |
Bill Alexander
|
|
|
|
Telephone call | | | 5/6/2002 | | DONE |
|
|
|
CALLED DON PERMIT READY 5-6-02
|
Sprinkler Plan Check | 4/5/2002 | | 4/18/2002 | | FAIL |
Bill Alexander
|
|
|
Lacking all elevation pressure loss in the attic sprinkler protection calculations. Lack proper coverage due to missing draft stops, skylight/soffits in the attic and incorrect use of attic head. Questions on shower stall. Questioned coverage on opening from ground floor to 3rd floor roof next to inside stairs. Need to calculate the most demanding single head demand on the 3rd floor.
|
Meeting | | | 4/18/2002 | | DONE |
|
|
|
Met with Don Weland and Bob Knight on this project and discussed items listed in the failed activity review. 9:30 AM.
|
Telephone call | | | 4/17/2002 | | DONE |
|
|
|
Called Don Weland (Shilo-Designer) and illustrated problems with attic system and had enough to deny plans. Continuing with wet system.
|
Application received | | | 4/5/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|