| DOC - Permit Finaled | 8/23/2002 | 8/23/2002 | 8/23/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 8/23/2002 11:17:19 AM
|
| INSP-Final Inspection | 8/22/2002 | 8/22/2002 | 8/22/2002 | P | PASS |
Troy Cobbley
|
|
|
Fire sprinklers finaled 8/23/2002 11:17:14 AM
|
| INSP-Sprinkler Rough-in/Hydro | 8/19/2002 | 8/20/2002 | 8/20/2002 | A | PASS |
Troy Cobbley
|
|
|
System #3 aboveground hydro test OK but was witnessed by the general contractor. Roughin in gym and auditorium ok except for thru bolts are required for the EQ attachments to the brick walls 8/20/2002 4:06:20 PM
|
| Miscellaneous action | | | 8/13/2002 | | DONE |
|
|
|
Received chemical list showing quantities and locations. (Format was not consistant in detail and/or locations). Emailed Hummel Architects-Ed Daniels
A. All chemicals are located in "Room 195", yet Rooms 23, 24 and 25 (all listed under 195) are not shown or identified on any plans we have on file? Please clarify the rooms under rooms breakdown provided.
B. It also appears an acid cabinet is also located in "Room 195".
Known requirements as submitted:
1. Room 23 will require Ordinary Group 1 area/density/spacing fire sprinkler protection.
2. Room 24 will require Ordinary Group 1 area/density/spacing fire sprinkler protection.
3. Room 27 will require Ordinary Group 1 area/density/spacing fire sprinkler protection.
If all these "rooms" are located in the Science Classroom 195....then it (#195) shall require Ordinary Group 1 area/density/spacing fire sprinkler protection minimum.
|
| INSP-Sprinkler Rough-in/Hydro | 8/2/2002 | 8/2/2002 | 8/2/2002 | P | PASS |
Troy Cobbley
|
|
|
areas 3d and 3f OK to cover. System #2 hydro test OK 8/2/2002 2:37:38 PM
|
| INSP-Supply line flush | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | PASS |
Troy Cobbley
|
|
|
flush of underground OK 7/25/2002 9:08:41 AM
|
| INSP-Sprinkler Rough-in/Hydro | 7/24/2002 | 7/25/2002 | 7/25/2002 | A | PASS |
Troy Cobbley
|
|
|
hydro test for the underground, fdc, riser header and the overhead system east area OK 7/25/2002 1:18:48 PM
|
| INSP-Sprinkler Rough-in | 7/22/2002 | 7/23/2002 | 7/23/2002 | A | PART |
Troy Cobbley
|
|
|
Multiple areas OK for cover. See on site approved plans for specific areas approved for cover 7/23/2002 2:26:47 PM
|
| INSP-Supply line flush | 7/2/2002 | 7/3/2002 | 7/3/2002 | P | PART |
Troy Cobbley
|
|
|
supply line and FDC are ok for cover. They both still need to be hydro tested and flushed 7/3/2002 1:50:15 PM
|
| INSP-Supply line flush | 6/27/2002 | 6/28/2002 | 6/28/2002 | A | PASS |
Troy Cobbley
|
|
|
Underground OK to cover. Hydro or flush not done 6/28/2002 11:42:35 AM
|
| Inspection Record Card- Fire | 6/6/2002 | | 6/6/2002 | | DONE |
|
|
|
|
| Telephone call | | | 6/6/2002 | | DONE |
|
|
|
CALLED BRAD 6-6-02///DLD
|
| Issue and Print Permit | | | 6/6/2002 | | DONE |
|
|
|
|
| Telephone call | | | 6/5/2002 | | DONE |
|
|
|
left mess that permit is ready
|
| Plan assigned to (Bill) | 5/31/2002 | | 6/5/2002 | | DONE |
|
|
|
6/5/2002 13:24:23 JWA - activity updated through activity FIRA22 from case FIR02-00217.
|
| Sprinkler Plan Check | 5/31/2002 | | 6/5/2002 | | PASS |
Bill Alexander
|
|
|
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2002 | | DONE |
Bill Alexander
|
|
|
|
| Application received | | | 5/31/2002 | | |
|
|
|
|
| Case Summary | | | | | DONE |
|
|
|
|