Permit Information
Permit NumberFIR02-00228
StatusFinaled
Name PROTEX
Site Address 715 S CAPITOL BLVD
Project Namealm-Boise City Library
Customer Number 
ePlanReview 
Description
Boise City Library - To install a new fire alarm system in this existing building. The system will include manual pull stations, sprinkler system and fire pump monitoring, smoke detection for air handler shutdown and smoke damper release, elevator recall, monitoring of a Halon extinguishing system, and a/v annunciation.
The associated building permit (BLD 01-03082) is to perform elevator, fire alarm, and security upgrades to the Boise City Public Library. Work is to include new storefront doors, new doorways in front elevator shaft #1 at the 2nd and 3rd floors, new smoke control doors on all doorways in front elevator shaft #1, upgrades to the elevator machine room, security upgrades to selected doors, and the modernization of two elevators.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  7/26/2004 DONE
INSP-Final Inspection5/22/20035/22/20035/22/2003APASS
DetailsRick Jackson
DOC - Permit Finaled5/22/20035/22/20035/22/2003APASS
DetailsRick Jackson
INSP-Final Inspection5/20/20035/21/20035/21/2003AFAIL
DetailsRick Jackson
this is grants cell. If we can do this at 8.00AM. Thank you Terry; Phone #: ###-#### Internet Inspection Request from: Terry Owsley need maps of initiating devices and Record of Completion; strobes synch'd 5/21/2003 7:49:40 AM
INSP-Final Inspection5/9/20035/13/20035/13/2003AFAIL
DetailsRick Jackson
This is Grants cell. This needs to be done at 7:00 am. Have a great day.; Phone #: ###-#### Internet Inspection Request from: Terry Owsley not synchronized; maps with initiating devices; need better descriptors at FACP 5/13/2003 8:41:27 AM
INSP-Final Inspection5/5/20035/9/20035/8/2003ACANC
DetailsRick Jackson
This is Grants Cell. Needs to be tested at 7:00 am if thats OK
Have a great day.; Phone #: ###-#### Internet Inspection Request from: Terry Owsley called Rob of Protex and told him I would not be able to do this inspection on 5/09 and he said he would reschedule for next week 5/8/2003 1:10:59 PM
INSP-Final Inspection4/24/20034/28/20034/28/2003ANR
DetailsRick Jackson
This is grants Cell.
Thank you ; Phone #: ###-#### Internet Inspection Request from: Terry Owsley talked to Grant and they will reschedule when ready 4/28/2003 1:47:17 PM
INSP-Final Inspection4/22/20034/25/20034/24/2003ACANC
DetailsRick Jackson
This is Grants Cell
Thanks Terry; Phone #: ###-#### Internet Inspection Request from: Terry Owsley Inspection cancelled from web by: Terry Owsley
INSP-Final Inspection2/21/20032/24/20032/24/2003ANR
DetailsRick Jackson
Grant Ahten; Phone #: ###-#### Internet Inspection Request from: Terry Owsley per phone call from Rob this inspection won't be ready as they have determined that sprinkler control valves aren't supervised by the alarm panel; he will call when ready 2/24/2003 1:23:52 PM
INSP-Final Inspection2/7/20032/12/20032/12/2003AFAIL
DetailsRick Jackson
Phone #: ###-#### Internet Inspection Request from: Terry Owsley inspection stopped due to: horns not working on all floors; strobes not in sync; south area of first floor devices not being recognized. Also need device location maps at FACP. Will need to test all devices, notification circuits; troubles; elevator recall; pump supervision - start test from scratch 2/12/2003 8:52:48 AM
FIR-Aging Inspection1/28/20031/28/20031/28/2003 NR
DetailsTroy Cobbley
I spoke with Grant, who is with Protex and he stated that they were waiting for the elevators to get signed off before they called for inspection on the fire alarm system. He stated that the inspection would probably be called in next week 1/28/2003 9:40:20 AM
Issue and Print Permit  10/29/2002 DONE
Alarm Plan Check10/23/2002 10/25/2002 PASS
Approved with conditions based on resubmittal revisions completed 10/25/02 by Protex and Farren.
PLANS/APPL TAKEN TO FRONT DESK  10/25/2002 DONE
Inspection Record Card- Fire10/25/2002 10/25/2002 DONE
Telephone call  10/25/2002 DONE
permit ready and fees due
Alarm Plan Check10/7/2002 10/18/2002 HOLD
10/7/02 resubmittal package not acceptable. HOLD- for Protex to come in on Monday to properly assemble the resubmittal into complete sets, identify changes, and address all items on the previous review.
Alarm Plan Check9/10/2002 9/20/2002 FAIL
9/10/02-REsubmittal-CONDITIONAL approval given to install subject to receipt and approval of resubmittal before final inspection and test can be conducted. Written review comments discussed with Rob at Protex and faxed to Protex and designer, Farren Engr'g.
Plan assigned to (SAM)9/9/2002 9/9/2002 DONE
REMOVED READY STATUS WHITCH WAS DONE IN ERROR.
Meeting  6/25/2002 DONE
Meting held at Library with John Farrin( Farrin Engineering), Rob Ahten (protex) to review questions on-site. Reviewed all comments from my initial review. I agreed to use of ceiling mounted area SD's directly above the wall-mounted air conditioning units for smoke detection/fan shut down. They will revise plans and resubmit per our discussion and all other agreements.
Plan assigned to (SAM)6/5/2002 6/19/2002 DONE
6/19/2002 10:13:42 SLR - activity updated through activity FIRA22 from case FIR02-00228.
Alarm Plan Check  6/19/2002 FAIL
Numerous issues with plan review; agreed with Protex and Farren engineering to have a meeting to discuss the issues rather than the time consuming effort to write up a complete review. Meeting scheduled with Farren Engr. for 6/25, 9:00 AM at City Hall.
Application received  6/5/2002