Agreement of Future work | 8/1/2002 | 10/1/2003 | 7/24/2003 | | |
|
|
|
letter dated 7-29-02; School Principal agrees that by 10-1-03 they will either install smoke detectors in beam pockets or install ceiling with appropriate SD to complete this Permit. Work Completed per FIR03-00314.
|
INSP-Final Inspection | 1/14/2003 | 1/14/2003 | 1/14/2003 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm system to be finaled per Sam Rogers since upgrade agreement has been made. To be completed october 1, 2003
|
DOC - Permit Finaled | 1/14/2003 | 1/14/2003 | 1/14/2003 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 1/14/2003 12:53:05 PM
|
INSP-Final Inspection | 8/15/2002 | 8/16/2002 | 8/16/2002 | A | PART |
Troy Cobbley
|
|
|
Fire alarm system given a temporary occupancy until the layin ceiling tile is installed which will eliminate the beam pockets and the requirement for smoke detectors in each one. This work will be done no later than Oct 1 2003 per letter agreed upon by Dave Miller with the Boise Fire Dept 8/16/2002 10:20:32 AM
|
INSP-Alarm Testing | 7/25/2002 | 7/26/2002 | 7/26/2002 | A | FAIL |
Troy Cobbley
|
|
|
signals to the monitoring station are incorrect, a/v's are overspaced in classrooms, smoke detectors overspaced due to beams in corridors and rooms. I stopped the inspection. Basically inspection needs to start at the beginning. 7/26/2002 10:35:22 AM
|
Plan assigned to (SAM) | 6/24/2002 | | 7/2/2002 | | DONE |
|
|
|
7/2/2002 10:58:26 SLR - activity updated through activity FIRA22 from case FIR02-00253.
|
Alarm Plan Check | | | 7/2/2002 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/2/2002 | | 7/2/2002 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/2/2002 | | DONE |
|
|
|
|
Application received | | | 6/24/2002 | | |
|
|
|
|