INSP-Final Inspection | 3/23/2004 | 3/23/2004 | 3/23/2004 | P | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 3/23/2004 | 3/23/2004 | 3/23/2004 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 3/23/2004 3:17:23 PM
|
INSP-Supply line flush | 8/2/2002 | 8/5/2002 | 8/5/2002 | A | FAIL |
Troy Cobbley
|
|
|
the thrust block pored by the contractor at the united water tie-in completly covers all of the pipe and fittings. There is no way to verify pipe, fittings or installation. I left correction notice asking contractor to remove thrust block so items can be verified 8/5/2002 9:13:40 AM
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2002 | 8/5/2002 | 8/5/2002 | A | PASS |
Troy Cobbley
|
|
|
Underground tie-in to the united water line OK for cover
|
INSP-Sprinkler Rough-in/Hydro | 8/5/2002 | 8/5/2002 | 8/5/2002 | P | PASS |
Troy Cobbley
|
|
|
bedding OK for underground supply. Underground OK for cover
|
INSP-Supply line flush | 7/26/2002 | 7/29/2002 | 7/29/2002 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/26/2002 at 11:11:03. Contact: ###-####. not connected to 12 inch UW line; the 12 inch is about 2 feet below grade; TVFP will have to fix this problem; thrust blocks and remainder okay to cover; no flush today - cover inspection only 7/29/2002 9:44:30 AM
|
Inspection Record Card- Fire | 7/22/2002 | | 7/22/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/22/2002 | | DONE |
|
|
|
called greg permit ready 7-22-02///dld
|
Issue permit | | | 7/22/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 7/18/2002 | | 7/22/2002 | | DONE |
|
|
|
7/22/2002 11:28:07 JWA - activity updated through activity FIRA22 from case FIR02-00294.
|
Sprinkler Plan Check | 7/19/2002 | | 7/22/2002 | | DONE |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2002 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 7/18/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|