INSP-Final Inspection | 1/2/2003 | 1/3/2003 | 1/3/2003 | A | PASS |
Troy Cobbley
|
|
|
GREG; Phone #: ###-#### Internet Inspection Request from: Darla Downs
|
DOC - Permit Finaled | 1/3/2003 | 1/3/2003 | 1/3/2003 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 1/3/2003 3:54:23 PM
|
INSP-Sprinkler Rough-in | 9/12/2002 | 9/16/2002 | 9/16/2002 | P | FAIL |
Rick Jackson
|
|
|
fire pump test; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung pump test was okay; see approved plans for areas failed - need additional EQ in storage area; heads overspaced by wall in SE storage area; verify heads in carasuels for type commodity; fire caulk penetration in occ separation wall; add clamp on 4 way in hallway; addadditional spare heads in head box; verify all end of lines have hanger within 12 inches as system is over 100 psi now; lower stock to below 22 feet (recommend markers on racks to identify 22 ft; add calc stickers, etc; inspector to witness test of all pump controller/tampers, etc 9/16/2002 2:56:56 PM
|
Issue permit | | | 9/11/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/9/2002 | | 9/9/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/9/2002 | | DONE |
|
|
|
PERMIT READY
|
Plan assigned to (Bill) | 7/31/2002 | | 9/9/2002 | | DONE |
|
|
|
9/9/2002 09:55:25 JWA - activity updated through activity FIRA22 from case FIR02-00307.
|
Sprinkler Plan Check | 9/6/2002 | | 9/9/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/9/2002 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 8/21/2002 | | 8/27/2002 | | PART |
Bill Alexander
|
|
|
OK to proceed temporarilly. Requires clarification and revised plans prior to final plan acceptance. No calling for inspection allowed under this approval. Reference review notes.
|
Miscellaneous action | | | 8/27/2002 | | DONE |
|
|
|
Returned plans to front desk for calling and returning for minimum requirement resubmittal.
|
Telephone call | | | 8/27/2002 | | DONE |
|
|
|
plans denied called to have them picked up
|
Sprinkler Plan Check | 7/31/2002 | | 8/7/2002 | | FAIL |
Bill Alexander
|
|
|
Requires pump supply cushion, backflow, forward test connection, re-calculations, commodity verification, existing/new hose stations with rack layouts, current design "cover sheet", earthquake calcs with correlating braces, dimensioning of heads/lines, head characteristics.
|
Miscellaneous action | | | 8/7/2002 | | DONE |
Bill Alexander
|
|
|
Faxed review comments and returned plans to front desk for calling and returning to sprinkler contractor.
|
Telephone call | | | 8/7/2002 | | DONE |
|
|
|
CALLED TO HAVE PLANS PICKED UP FOR DENIAL
|
Miscellaneous action | | | 7/29/2002 | | DONE |
|
|
|
Greg Patrick requested pull submittal - wrong calculations used in the calcs. 11:07am.
|
Application received | | | 7/25/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|