INSP-Final Inspection | 10/2/2003 | 10/2/2003 | 10/2/2003 | P | PASS |
Rick Jackson
|
|
|
john; Phone #: ###-#### Internet Inspection Request from: Darla Downs all items completed 10/2/2003 1:20:54 PM
|
DOC - Permit Finaled | 10/2/2003 | 10/2/2003 | 10/2/2003 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 10/2/2003 1:20:57 PM
|
INSP-Final Inspection | 8/18/2003 | 8/19/2003 | 8/19/2003 | A | FAIL |
Troy Cobbley
|
|
|
JIM; Phone #: ###-#### Various hangers on the 2 1/2" branchlines in the warehouse exceed exception #2 of NFPA 13 6-4.5.3 and therefore require E.Q. brace. Provide fourway bracing at all risers per NFPA 13 6-4.5.5. Provide forward flow flush. Walk thru entire project to verify follow up notes and canopies. Verify all review notes have been followed. Provide signage and stripping for FDC access per conversation 8/19/2003 1:31:36 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/10/2003 | 7/10/2003 | 7/10/2003 | P | PART |
Troy Cobbley
|
|
|
conference room in the northwest corner of the building is ok to cover. One pendant is not installed per plan. The sprinkler fitter said he would correct it. Its location is marked on the plans and will be checked on the next inspection 7/10/2003 2:19:01 PM
|
INSP-Sprinkler Rough-in | 5/16/2003 | 5/16/2003 | 5/16/2003 | P | PART |
Troy Cobbley
|
|
|
jim; Phone #: ###-#### Rooms where the sprinkler piping can be covered are marked on the job site approved plans. Piping in kitchen area exceeds heads for 1 1/4" pipe size and electrical room needs fire sprinkler protection 5/16/2003 4:09:20 PM
|
INSP-Sprinkler Rough-in | 4/17/2003 | 4/17/2003 | 4/17/2003 | P | PART |
Rick Jackson
|
|
|
ADAM; Phone #: ###-#### Internet Inspection Request from: Darla Downs identified on plans for area okay to cover; will recheck for two retaining straps as marked on plans 4/17/2003 3:03:09 PM
|
INSP-Sprinkler Rough-in | 2/20/2003 | 2/20/2003 | 2/20/2003 | P | PART |
Troy Cobbley
|
|
|
adam; Phone #: ###-#### The main lobby area and corridor sprinkler piping is ok to cover. The area is shown on the approved sprinkler plan. 2/20/2003 3:25:17 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2003 | 2/10/2003 | 2/10/2003 | P | PART |
Troy Cobbley
|
|
|
###-#### jim The sprinkler piping in the plate room 222 on the second floor can be covered. One sprinkler head needs to be relocated and a hanger needs to be added. Locations are shown on the approved plans. The sprinkler pendants in the corridor outside of this room are overspaced and need corrected 2/10/2003 3:12:04 PM
|
INSP-Sprinkler Rough-in | 2/3/2003 | 2/3/2003 | 2/3/2003 | P | PART |
Troy Cobbley
|
|
|
###-#### The main lobby area sprinkler piping can be covered. The main sprinkler piping as it penatrates the block wall in two locations will need to be provided with adequate clearance. Hangers will need to be added at two locations on the existing main 2/3/2003 3:13:40 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/17/2002 | 12/17/2002 | 12/17/2002 | P | PART |
Troy Cobbley
|
|
|
hydro test on the second floor is ok 12/17/2002 4:02:07 PM
|
Issue permit | | | 12/16/2002 | | |
|
|
|
|
Sprinkler Plan Check | 12/4/2002 | | 12/13/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2002 | | DONE |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 12/4/2002 | | 12/4/2002 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/4/2002 | | DONE |
Bill Alexander
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 11/27/2002 | 11/27/2002 | 11/27/2002 | P | PART |
Troy Cobbley
|
|
|
areas that are approved for cover have been marked on the approved job site plans with todays date 11-27-02 11/27/2002 3:02:59 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/22/2002 | 11/22/2002 | 11/22/2002 | P | PASS |
Troy Cobbley
|
|
|
the specific areas that have roughin approved and are ok to cover have been marked on the job site approved sprinkler plans with todays date and signature 11-22-02 11/22/2002 4:35:27 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/5/2002 | 9/5/2002 | 9/5/2002 | P | PASS |
Troy Cobbley
|
|
|
rough-in for sprinklers in the new addition is OK. I gave permission to cover pipe. Hydro test for the sprinkler piping in the new addition is OK 9/5/2002 2:53:04 PM
|
INSP-Sprinkler Rough-in/Hydro | 8/20/2002 | 8/21/2002 | 8/21/2002 | P | PART |
Troy Cobbley
|
|
|
sprinklers in telemarketing area is OK for cover except for retaining staps and eq bracing needing to be brought up to code 8/21/2002 2:07:32 PM
|
Issue and Print Permit | | | 8/19/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/16/2002 | | 8/16/2002 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/13/2002 | | 8/15/2002 | | PASS |
Bill Alexander
|
|
|
Addressing of Rolled Paper Storage areas require addressing prior to permit finaling.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2002 | | DONE |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 7/29/2002 | | 7/30/2002 | | DONE |
|
|
|
7/30/2002 07:54:44 JWA - activity updated through activity FIRA22 from case FIR02-00311.
|
Sprinkler Plan Check | 7/29/2002 | | 7/30/2002 | | PART |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2002 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 7/30/2002 | | 7/30/2002 | | DONE |
|
|
|
|
Telephone call | | | 7/30/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Issue and Print Permit | | | 7/30/2002 | | DONE |
|
|
|
|
Application received | | | 7/29/2002 | | |
|
|
|
|