INSP-Final Inspection | 10/10/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Troy Cobbley
|
|
|
fire sprinklers finaled 10/11/2002 10:50:25 AM
|
DOC - Permit Finaled | 10/11/2002 | 10/11/2002 | 10/11/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 10/11/2002 10:50:33 AM
|
INSP-Conference | 9/25/2002 | 9/26/2002 | 9/26/2002 | A | DONE |
Troy Cobbley
|
|
|
inspection was for a sprinkler rough-in for the corridors and restrooms on the first and second floors. Piping is OK to cover. Contractor will be adding a sidewall sprinkler head beneath the stairs and boxing in the first floor landing 9/26/2002 8:55:36 AM
|
Issue and Print Permit | | | 8/9/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/8/2002 | | 8/8/2002 | | DONE |
|
|
|
|
Telephone call | | | 8/8/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Plan assigned to (Bill) | 7/30/2002 | | 8/8/2002 | | DONE |
|
|
|
8/8/2002 14:51:40 JWA - activity updated through activity FIRA22 from case FIR02-00314.
|
Sprinkler Plan Check | 7/31/2002 | | 8/8/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2002 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 7/30/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|