INSP-Final Inspection | 9/25/2002 | 9/25/2002 | 9/25/2002 | A | PASS |
Troy Cobbley
|
|
|
fire alarm system finaled
|
DOC - Permit Finaled | 9/25/2002 | 9/25/2002 | 9/25/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 9/25/2002 10:25:14 AM
|
INSP-Alarm Testing | 9/18/2002 | 9/19/2002 | 9/19/2002 | A | FAIL |
Troy Cobbley
|
|
|
provide verification that the 10ah batteries are OK to use, fix damper that won't close, relocate duct detector or first take off on hvac unit 9/19/2002 12:55:43 PM
|
Plan assigned to (SAM) | 8/7/2002 | | 9/10/2002 | | DONE |
|
|
|
9/10/2002 15:41:09 SLR - activity updated through activity FIRA22 from case FIR02-00321.
|
Alarm Plan Check | 8/27/2002 | | 9/10/2002 | | PASS |
|
|
|
Resubmittal still incorrect; Paul Highley, Synergy, to refax corrected calc's which include standby current draw for the NAC panel. However, the battery size shown is more than adequate, so plans are being approved; subbject to the re-calc's being reubmitted for City permanent records.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/10/2002 | | DONE |
|
|
|
CALLED WES PERMIT READY 9-10-02///DLD
|
Issue permit | | | 9/10/2002 | | |
|
|
|
|
Alarm Plan Check | | | 8/23/2002 | | FAIL |
|
|
|
CONDITIONAL APPROVAL granted to start installation work subject to resubmittal. No final inspection allowed until permit is issued. Called Synergy to discuss;designer not available; faxed review comments to Synergy.
|
Application received | | | 8/7/2002 | | |
|
|
|
|