(F) Reprint permit | | | 1/4/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 6/16/2004 | 6/17/2004 | 6/17/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled 6/17/2004 8:04:24 AM
|
DOC - Permit Finaled | 6/17/2004 | 6/17/2004 | 6/17/2004 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 6/17/2004 8:04:28 AM
|
INSP-Final Inspection | 6/1/2004 | 6/3/2004 | 6/3/2004 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 6/1/2004 at 7:57:32 AM. Contact: ###-####. AV12-3 not working; need to test new tamper/flow; need as-builts to verify changes made to all NAC's as they don't match plans; NAC 2 circuits wired backwards at panel; labels on AV's not correct 6/3/2004 11:52:23 AM
|
Inspection Record Card- Fire | 4/21/2004 | | 4/21/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/21/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/21/2004 | | DONE |
|
|
|
permit ready and fee due
|
CHANGE STATUS TO (ISS) | | | 4/21/2004 | | DONE |
|
|
|
pd permit
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 4/20/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
Plan resubmittals received | | | 4/12/2004 | | DONE |
|
|
|
|
INSP-Conference | 4/14/2004 | 3/16/2004 | 3/16/2004 | P | DONE |
Troy Cobbley
|
|
|
I met with the project engineer and the general contractor to discuss items listed on the plan modifications. The items are a/v coverage possibly lacking in areas listed on the plan review comments. Upon field inspection it was determined that a/v coverage was adequate for the listed areas.
|
Alarm Plan Check | | | 2/3/2004 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Chris Willis 2/3/04.
|
Plan resubmittals received | | | 1/14/2004 | | |
|
|
|
|
INSP-Final Inspection | 8/20/2003 | 8/22/2003 | 8/22/2003 | A | FAIL |
Troy Cobbley
|
|
|
Sync strobes in room 181 (av5-17) and in corridor 152, horns in mech. room 218 are not 15db above ambient sound level, provide map for facp, provide locks on breakers, strobes in Press 100g and storage 189c exceed maximum coverage off wall (see plan). THIS WAS A PARTIAL INSPECTION. It appears plans and review notes have not been followed. I'm requesting the fire alarm contractor to reinspect before my next inspection 8/22/2003 1:59:49 PM
|
INSP-Final Inspection | 5/13/2003 | 5/20/2003 | 5/20/2003 | P | PART |
Troy Cobbley
|
|
|
###-#### See approved alarm for exact locations that have been approved with todays date. Area was around elevator #2 5/20/2003 2:30:48 PM
|
INSP-Conference | 4/16/2003 | 4/16/2003 | 4/16/2003 | A | DONE |
Troy Cobbley
|
|
|
I met with mechanical engineer Bob Tikker and architect Marv Merkal and discussed the placement of the duct smoke detectors on units 1, 2 and 3. They have decided to stick with the UMC code and provide the duct smoke detectors on the supply side of these units
|
INSP-Conference | 4/7/2003 | 4/9/2003 | 4/9/2003 | A | DONE |
Troy Cobbley
|
|
|
###-#### Met with contractors about placement of the duct smoke detectors. Nothing could be completed since the mechanical engineer and the mechanical contractor were not present but the architect left with more knowledge of mechanical system 4/9/2003 9:52:03 AM
|
INSP-Conference | 4/1/2003 | 4/2/2003 | 4/2/2003 | A | DONE |
Troy Cobbley
|
|
|
mark; Phone #: ###-#### Discussed the placement of the remote annunciator and placement of duct smoke detectors. I gave Jim permission to cover the sprinkler piping in the old print room on the east side 1st floor 4/2/2003 9:28:11 AM
|
INSP-Alarm Testing | 1/1/2003 | 1/2/2003 | 1/2/2003 | A | PART |
Troy Cobbley
|
|
|
2nd floor office area ok for occupancy. See onsite approved plan for exat location with 1-2-03 date 1/2/2003 9:50:12 AM
|
INSP-Alarm Testing | 12/10/2002 | 12/11/2002 | 12/11/2002 | A | FAIL |
Troy Cobbley
|
|
|
the NAC panel in electrical room 125 does not report a trouble when ac power is off and the standby current draw exceeds the calculations, two exit signs in the open office 126 do not work, smoke detectors at the top of the elevator shaft does not recall to the first floor but since there are no sprinklers at the top of the elevator the heat and the smoke should be removed, the heat detector is more than 24" from the sprinkler pendant, 12/11/2002 12:56:02 PM 12/11/2002 12:56:39 PM
|
INSP-Final Inspection | 11/19/2002 | 11/21/2002 | 11/21/2002 | A | PART |
Troy Cobbley
|
|
|
The areas inspected and passed for this part of the phase are marked on the job site plans. Current draw for the nac panels is greater than what is stated on the calcs. Contractor needs to install the 10 ah batteries as stated on the plans, label the remote leds, repair one exit sign 11/21/2002 10:27:50 AM
|
Issue and Print Permit | | | 10/31/2002 | | DONE |
|
|
|
|
Alarm Plan Check | 10/30/2002 | | 10/30/2002 | | PASS |
Sam Rogers
|
|
|
Approved with Conditions
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2002 | | DONE |
Sam Rogers
|
|
|
|
Inspection Record Card- Fire | 10/30/2002 | | 10/30/2002 | | DONE |
|
|
|
|
Telephone call | | | 10/30/2002 | | DONE |
|
|
|
permit ready and fees due
|
Alarm Plan Check | 10/3/2002 | | 10/15/2002 | | FAIL |
|
|
|
Resubmittal. Conditional approval granted to begin installation. Final inspection not allowed prior to receipt of the required resubmittal and issuance of the permit. Review faxed to Simplex and Eidam.
|
Alarm Plan Check | | | 9/11/2002 | | FAIL |
|
|
|
Plans inadequate. Discussed with Simplex; faxed to Simplex and Eidam, designer.
|
Miscellaneous action | | | 9/5/2002 | | DONE |
|
|
|
e-mail received today from UFC inspector Troy cobbley, indicating fire alarm horn/strobes have been installed, without approved plans; no FA permit has been issued. Power Plus, the installing electrical contractor was advised by Troy that all work is to cease until a Fire Alarm permit and approved alarm plans are on site. Sinplex advised by phone that a double permit fee will apply to the Fire alarm permit.
|
Application received | | | 9/3/2002 | | |
|
|
|
|