Permit Information
Permit NumberFIR02-00364
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 5550 W MORRIS HILL RD
Project NameSPR ADA CNTY CORONER - MORGUE
Customer Number 
ePlanReview 
Description
(ADA COUNTY CORONER - MORGUE) This building requires fire sprinklered for area increase. To install fire sprinklers in a 3,450-ft/2 morgue within an existing 24,000 square foot warehouse/office building, to be used by the Ada County Coroner's Office. The Coroner will occupy the 3,450-ft/2 morgue, the 2,400 ft/2 1st floor office area, and the 2,000 ft/2 2nd floor office area (7,850 ft/2 total permitted work area). Work is related to 2 toilet/shower rooms, 2 upgraded toilet rooms, new interior nonbearing walls, a 300 square foot mechanical mezzanine, replaced concrete slabs, foam plastic freezer/cooler, and suspended ceilings all per approved drawings, engineering, and plan review conditions on file. The fire sprinkler system shall comply with NFPA 13-1999 as regulated by the Fire Department. The fire sprinkler system work shall comply with NFPA 13-1999, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD02-00031.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  10/4/2004  
Agreement of Future work9/11/200212/30/20046/20/2003 PASS
County agrees to correct AS deficiencies and fuklly sppk the bldg by fiscal year 03-04 or sooner. Refer to Upgrade Agreement dated 8/22/02 David Logan ADA County Director of Operations.
INSP-Final Inspection11/4/200211/4/200211/4/2002PPASS
DetailsTroy Cobbley
###-####
DOC - Permit Finaled11/4/200211/4/200211/4/2002PPASS
DetailsTroy Cobbley
Finaled by inspector at 11/4/2002 3:01:27 PM
INSP-Final Inspection10/3/200210/3/200210/3/2002PCANC
DetailsTroy Cobbley
contractor did not call for this inspection 10/3/2002 3:48:18 PM
INSP-Sprinkler Rough-in/Hydro9/23/20029/24/20029/24/2002PPASS
DetailsTroy Cobbley
add sprinkler head in entry and provide a hanger on pendant over cooler 9/24/2002 3:28:03 PM
INSP-Sprinkler Rough-in/Hydro9/23/20029/25/20029/23/2002ACANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 09/23/2002 at 16:01:13. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 09/23/2002 at 16:04:51.
Meeting  9/13/2002 DONE
DetailsBill Alexander
September 13, 2002 - Walked through 1:30pm - Met with Architect (Dan Kauffman), Ada County building maintenance, Fire Sprinkler Contractor, General Contractor and inspected facility for new and existing UFC fire protection issues. Found some existing offices not sprinklered, High-piled combustible storage 12'-0" high with 36" wide, single rack, solid shelf, storage of Class II commodities up to 15'-0". Minimum aisle widths are 40" (one side) and 44" (the other). System (installed in 1963+-), appears to be designed for OH pipe scheduled occupancy with a 120 ft/2 spacing, limiting it to 12'-0" maximum. UFC Article 81 would have to be addressed in this area of occupancy.
Miscellaneous action  9/12/2002 DONE
DetailsBill Alexander
Received copy of approved letter requested in review comments list, item letter "B. a."
Issue permit  9/11/2002 DONE
Telephone call  9/10/2002 DONE
CALLED BOB PERMIT READY 9-10-02///DLD
Plan assigned to (Bill)9/6/2002 9/10/2002 DONE
9/10/2002 15:37:57 JWA - activity updated through activity FIRA22 from case FIR02-00364.
Sprinkler Plan Check9/10/2002 9/10/2002 PASS
DetailsBill Alexander
Approved pending structure is fully protected.
PLANS/APPL TAKEN TO FRONT DESK  9/10/2002 DONE
DetailsBill Alexander
Application received  9/6/2002  
Case Summary    DONE
Inspection Record Card- Fire9/16/2002