INSP-Final Inspection | 10/24/2002 | 10/24/2002 | 10/24/2002 | P | PASS |
Troy Cobbley
|
|
|
fire finaled
|
DOC - Permit Finaled | 10/24/2002 | 10/24/2002 | 10/24/2002 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 10/24/2002 2:45:34 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2002 | 10/14/2002 | 10/14/2002 | A | FAIL |
Troy Cobbley
|
|
|
rough-in for the TI is ok but can not be finaled untill the shell is finaled 10/14/2002 4:25:30 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2002 | 10/10/2002 | 10/10/2002 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 10/08/2002 at 11:41:01. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on 10/10/2002 at 11:22:39.
|
Inspection Record Card- Fire | 9/13/2002 | | 9/13/2002 | | DONE |
|
|
|
|
Telephone call | | | 9/13/2002 | | DONE |
|
|
|
permit ready and fees due
|
Issue and Print Permit | | | 9/13/2002 | | DONE |
|
|
|
|
Application received | | | 9/12/2002 | | |
|
|
|
|
Plan assigned to (SAM) | 9/12/2002 | | 9/12/2002 | | DONE |
|
|
|
9/12/2002 15:21:37 JWA - activity updated through activity FIRA22 from case FIR02-00373.
|
Sprinkler Plan Check | 9/12/2002 | | 9/12/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/12/2002 | | DONE |
Bill Alexander
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|