INSP-Final Inspection | 10/29/2002 | 10/30/2002 | 10/30/2002 | A | PASS |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 10/29/2002 at 13:43:14. Contact: ###-####.
|
DOC - Permit Finaled | 10/30/2002 | 10/30/2002 | 10/30/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 10/30/2002 9:08:55 AM
|
INSP-Final Inspection | 10/26/2002 | 10/28/2002 | 10/28/2002 | A | NR |
Troy Cobbley
|
|
|
cooler had not been installed yet 10/28/2002 1:56:18 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/22/2002 | 10/23/2002 | 10/23/2002 | A | FAIL |
Troy Cobbley
|
|
|
replace the painted sprinkler heads in the front and the rear of the TI space and relocate the sprinkler heads that are closer than 4" to the walls 10/23/2002 9:55:51 AM
|
Inspection Record Card- Fire | 10/14/2002 | | 10/14/2002 | | DONE |
|
|
|
|
Telephone call | | | 10/14/2002 | | DONE |
|
|
|
PERMIT READY AND FEES DUE
|
Issue and Print Permit | | | 10/14/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/9/2002 | | 10/14/2002 | | DONE |
|
|
|
10/14/2002 09:19:42 JWA - activity updated through activity FIRA22 from case FIR02-00404.
|
Sprinkler Plan Check | 10/10/2002 | | 10/14/2002 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/2002 | | DONE |
Bill Alexander
|
|
|
|
Application received | | | 10/9/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|