INSP-Final Inspection | 12/3/2002 | 12/4/2002 | 12/4/2002 | A | PASS |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 12/03/2002 at 15:51:58. Contact: ###-####.
|
DOC - Permit Finaled | 12/4/2002 | 12/4/2002 | 12/4/2002 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 12/4/2002 11:05:49 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/19/2002 | 11/20/2002 | 11/20/2002 | A | PASS |
Troy Cobbley
|
|
|
rough-in for the inrack sprinklers is ok, but they are not tied into the riser yet. The hydro test is ok. The wrong sprinkler heads have been installed and require changed or reapproved. The hose valve connection is incorrect 11/20/2002 3:59:00 PM
|
Issue and Print Permit | | | 11/13/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/11/2002 | | 11/12/2002 | | DONE |
|
|
|
11/12/2002 14:41:26 JWA - activity updated through activity FIRA22 from case FIR02-00407.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2002 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 11/12/2002 | | 11/12/2002 | | DONE |
|
|
|
|
Telephone call | | | 11/12/2002 | | DONE |
|
|
|
permit ready
|
Plan resubmittals received | | | 11/1/2002 | | PASS |
Bill Alexander
|
|
|
Building has Class III-A and 1-B flammable liquids and is limited with a S-1 Occupancy. Wholesale/retail sales (which was witnessed) would entail a building review for an M Occupancy, not an S-1.
Holding review till Jason Blais (Planner) can re-evaluate BLD.
11/12/2002-reviewed BLD and FIR (Approved).
|
Sprinkler Plan Check | 10/11/2002 | | 10/18/2002 | | FAIL |
Bill Alexander
|
|
|
Plan lacks required detail, no calculation verification, no verification of other "pile" storage, carpet racks not clarified, other racks storage is are not clarified, storage height exceeds design limit, etc.
|
Miscellaneous action | | | 10/18/2002 | | FAIL |
|
|
|
Work performed without a permit. Requires double fees and possible citation.
Sent Pre-citation letter 11/07/2002, (Certified Mail-Return Receipt)
|
Telephone call | | | 10/18/2002 | | DONE |
|
|
|
Called Owner and Requested meeting with owner, G.C. and fire sprinkler contractor to straighten issue with rack use and fire protection
|
Application received | | | 10/11/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|
Case Summary | | | | | |
|
|
|
|