Miscellaneous action | | | 5/28/2003 | | DONE |
|
|
|
Job was finaled by Troy without revised plans as requrested.
|
INSP-Final Inspection | 5/12/2003 | 5/12/2003 | 5/12/2003 | P | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 5/12/2003 | 5/12/2003 | 5/12/2003 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 5/12/2003 3:21:14 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/8/2003 | 5/9/2003 | 5/9/2003 | A | FAIL |
Troy Cobbley
|
|
|
Can not complete the fire sprinkler inspection until the fire alarm system is ready. The fire sprinkler connections to the fire alarm system are the only items left to complete, dry pipe riser and wet riser. 5/9/2003 11:29:27 AM
|
INSP-Final Inspection | 5/7/2003 | 5/8/2003 | 5/8/2003 | A | FAIL |
Troy Cobbley
|
|
|
Too many items wrong to list. see correction notice 5/8/2003 3:06:59 PM
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2003 | 5/7/2003 | 5/7/2003 | P | PART |
Troy Cobbley
|
|
|
Started the 24 hour test on the dry system at 1:30. Guage is at 45 psi
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/1/2003 | | DONE |
Bill Alexander
|
|
|
Resubmittals
|
Inspection Record Card- Fire | 5/1/2003 | | 5/1/2003 | | DONE |
|
|
|
|
Telephone call | | | 5/1/2003 | | DONE |
|
|
|
permit ready
|
Issue permit | | | 5/1/2003 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/30/2003 | | 5/1/2003 | | PASS |
Bill Alexander
|
|
|
Fire sprinkler plan/installation revision. (faxed) Need full sized sheets.
Troy passed off without revised plans.
|
Plan resubmittals received | | | 4/30/2003 | | DONE |
Bill Alexander
|
|
|
Fire sprinkler plan/installation revisions.
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2003 | 4/8/2003 | 4/8/2003 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 4/8/2003 at 8:13:02 AM. r/i of sanctuary - head has baggie and one head painted - see plans for exact locations 4/8/2003 4:02:39 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2003 | 4/7/2003 | 4/7/2003 | P | PART |
Troy Cobbley
|
|
|
See on site approved plans for locations to add upright heads and eq bracing. Other areas still need rough-in inspection 4/7/2003 12:15:41 PM
|
INSP-Sprinkler Rough-in/Hydro | 3/12/2003 | 3/13/2003 | 3/13/2003 | A | PART |
Troy Cobbley
|
|
|
sprinkler piping is ok to cover in rooms marked on the job site approved plans. Upright sprinkler heads to be added above the mens restroom 3/13/2003 1:36:49 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2003 | 2/12/2003 | 2/12/2003 | A | PART |
Troy Cobbley
|
|
|
Front canopy piping is OK to cover 2/12/2003 8:46:59 AM
|
Inspection Record Card- Fire | 11/19/2002 | | 11/19/2002 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/19/2002 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/24/2002 | | 11/18/2002 | | DONE |
|
|
|
11/18/2002 17:01:50 JWA - activity updated through activity FIRA22 from case FIR02-00423.
|
Sprinkler Plan Check | 11/12/2002 | | 11/18/2002 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 11/12/2002 | | DONE |
|
|
|
|
Sprinkler Plan Check | 10/24/2002 | | 11/1/2002 | | FAIL |
Bill Alexander
|
|
|
Calculation problems, sprinkler head problems, need some detailed plan clarifications, etc. (Reference review)
|
Miscellaneous action | | | 11/1/2002 | | DONE |
|
|
|
Took failed plans to front desk for calling and returning to contractor - 2:45pm
|
Application DENIED | | | 11/1/2002 | | DONE |
|
|
|
plans failed return to sender
|
Application received | | | 10/24/2002 | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|