INSP-Final Inspection | 11/21/2003 | 11/21/2003 | 11/21/2003 | P | PASS |
Troy Cobbley
|
|
|
finaled 7-3-2003
|
DOC - Permit Finaled | 11/21/2003 | 11/21/2003 | 11/21/2003 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 11/21/2003 12:16:01 PM
|
INSP-Final Inspection | 7/2/2003 | 7/3/2003 | 7/3/2003 | P | FAIL |
Troy Cobbley
|
|
|
Project not ready for a final inspection yet. Underground supply flush was OK though 7/3/2003 4:06:59 PM
|
INSP-Final Inspection | 6/30/2003 | 6/30/2003 | 6/30/2003 | P | FAIL |
Troy Cobbley
|
|
|
Install wiring connections in devices or boxes per NFPA 70 for all fire alarm devices 6/30/2003 3:04:39 PM
|
INSP-Final Inspection | 6/4/2003 | 6/5/2003 | 6/5/2003 | A | FAIL |
Troy Cobbley
|
|
|
Provide knox box, provide sign on fire alarm/riser door, clean up all duct detector wiring, rotate sample tube in duct detector in daycare(zone 128), provide filter for duct detector in Joey's Seafood, repair wiring and test hood in the Mongolian BBQ. 6/5/2003 11:07:33 AM
|
INSP-Final Inspection | 6/3/2003 | 6/4/2003 | 6/4/2003 | A | PART |
Troy Cobbley
|
|
|
Started the inspection. Was not able to finish. To be continued tomorrow. 6/4/2003 11:17:04 AM
|
INSP-Final Inspection | 5/29/2003 | 5/30/2003 | 5/29/2003 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 5/29/2003 at 9:38:27 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on May 29 2003 3:21PM.
|
INSP-Final Inspection | 5/23/2003 | 5/28/2003 | 5/27/2003 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 5/23/2003 at 2:41:24 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on May 27 2003 4:20PM.
|
INSP-Alarm Testing | 5/15/2003 | 5/16/2003 | 5/16/2003 | A | PART |
Troy Cobbley
|
|
|
The duct smoke detector over Basilio's restraunt that was previously not working now functions correctly 5/16/2003 10:30:17 AM
|
INSP-Alarm Testing | 5/9/2003 | 5/9/2003 | 5/9/2003 | P | FAIL |
Troy Cobbley
|
|
|
North hvac unit in the Basilio's restraunt would not operate. It is locked out until it can be repaired and tested. Smoke detector over panel, battery troubles, phone lines and pull station have been tested. No other items tested. This initial test was just to get the restraunt a temp occupancy. The main inspection to be called in next week. 5/9/2003 2:47:53 PM
|
Issue permit | | | 2/12/2003 | | DONE |
|
|
|
|
Telephone call | | | 2/10/2003 | | DONE |
|
|
|
Telcon with Dave Miller. The day care has a 1-hour occupancy separation around it and existing pull stations at all its exits. Agreed to accept the proposed Phase 1 plan, and not require Phase 2 or 3 or manual pulls and a/v outside the daycare occupany.
|
Alarm Plan Check | | | 2/10/2003 | | PASS |
|
|
|
resubmittal acceptable without Phase 2 and 3 as shown on plans, per FD approval and interpretation of IFC requirements.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/2003 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/10/2003 | | 2/10/2003 | | DONE |
|
|
|
|
Telephone call | | | 2/10/2003 | | DONE |
|
|
|
permit ready and fees due
|
Plan assigned to (SAM) | 11/6/2002 | | 2/10/2003 | | DONE |
|
|
|
2/10/2003 16:05:50 SLR - activity updated through activity FIRA22 from case FIR02-00432.
|
Plan resubmittals received | | | 1/31/2003 | | DONE |
|
|
|
discussed with Pat McKeegan; he has written Dave Miller proposing use of the IFC and his (McKeegan's) interpretation of its requirements to the new FA system. I will hold off doing a plan review of theis resubmittal until an answer is received from Dave Miller on FD's reply, specifically regarding extent of a/v alarms and pull stations.
|
Alarm Plan Check | | | 11/29/2002 | | PEND |
|
|
|
Delayed upgrade approved by Fire Dept in conjuction with a TOC approval for BLD02-02390. New alarm plans to be submitted after details of the upgrade program are determined by Feb 28, 2002.
|
INSP-Alarm Testing | 11/27/2002 | 11/27/2002 | 11/27/2002 | A | NR |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Millers permission for the California Marketplace TI until the fire alarm system has been permited and inspected. The owner has until 2-28-03 to complete work. See letter dated 11-21-02.
|
Alarm Plan Check | | | 11/14/2002 | | FAIL |
|
|
|
written review faxed to Peak and to Pet Conlon, Collier's Int'l.
|
Telephone call | | | 11/13/2002 | | DONE |
|
|
|
Telcon with Pete Conlon, Property mgr. They have hired Jim Falk, Apex Engineering, to review our comments and prepare a new FA system design. Fax a copy of our review to Pete for his use.
|
Alarm Plan Check | | | 11/8/2002 | | FAIL |
|
|
|
Plans have major deficiencies. An E3/125 occupancy tenant necessitates the "builidng have a manual alarm system; improper method shown for release of smoke dampers; separation from contiguous Shopco "building" not indicated. These deficiencies discussed with Steve Larson, Peak Alarm 11/8; he will discuss with Pete Conlon Property Mgr. Written review to be sent out next week.
|
Telephone call | | | 11/8/2002 | | DONE |
|
|
|
Called Steve Larson to advise of plans deficiencies; written review comments to be sent out next week.
|
Application received | | | 11/6/2002 | | |
|
|
|
|