Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR02-00436
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 873 E CITATION CT
Project NameSPR Bon Aire Industries
Customer Number 
ePlanReview 
Description
Bon Aire Industries * To install fire sprinkler protection in a new 26,050 ft/2, one story with mezzanine, warehouse and accessory office building, constructed of concrete tilt-up exterior walls and steel structural frame and roof joists. The mezzanine is 2800 ft/2. This permit also includes the underground fire service supply. The fire sprinklers are required for area increase. The fire sprinkler system work shall comply with NFPA 13-1999, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD02-01912.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary  8/6/2004  
INSP-Final Inspection5/19/20035/19/20035/19/2003PPASS
DetailsRick Jackson
DOC - Permit Finaled5/19/20035/19/20035/19/2003PPASS
DetailsRick Jackson
Finaled by inspector at 5/19/2003 3:52:17 PM
INSP-Sprinkler Rough-in/Hydro3/26/20033/26/20033/26/2003PPART
DetailsRick Jackson
ADAM; Phone #: ###-#### Internet Inspection Request from: Darla Downs hydro okay on overhead and underground 3/26/2003 4:00:53 PM
INSP-Supply line flush3/17/20033/19/20033/19/2003APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 3/17/2003 at 2:16:03 PM. Contact: ###-####. flush okay; sprinkler heads painted in office area 3/19/2003 10:11:33 AM
INSP-Conference1/23/20031/24/20031/23/2003APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 01/23/2003 at 13:01:06. Contact: ###-####. completed UG cover on 1/23 1/23/2003 2:47:55 PM
INSP-Sprinkler Rough-in1/23/20031/23/20031/23/2003PPART
DetailsRick Jackson
underground complete; okay to cover
INSP-Conference12/19/200212/19/200212/19/2002PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/19/2002 at 09:19:07. Contact: ###-####. conference about UG 12/19/2002 3:49:35 PM
INSP-Sprinkler Rough-in12/19/200212/19/200212/19/2002PPART
DetailsRick Jackson
UG r/i okay; stub out from building
Inspection Record Card- Fire12/17/2002 12/17/2002 DONE
Telephone call  12/17/2002 DONE
CALLED 12-17-02
Issue and Print Permit  12/17/2002 DONE
Plan assigned to (Bill)11/7/2002 12/16/2002 DONE
12/16/2002 14:54:31 JWA - activity updated through activity FIRA22 from case FIR02-00436.
Alarm Plan Check12/10/2002 12/16/2002 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  12/16/2002 DONE
DetailsBill Alexander
Plan resubmittals received  12/10/2002 DONE
Sprinkler Plan Check11/26/2002 12/9/2002 FAIL
DetailsBill Alexander
1. Where branch lines are larger than 2", the fire sprinkler shall be supplied by a riser nipple to elevate the sprinkler 13" for 2½" pipe. These dimensions shall be measured from the centerline of the pipe to the sprinkler deflector. NFPA 13:5-10.5.2.3)
2. Provide revised area "A" calculations incorporating the tee, riser nipple and elevation differences.
3. Provide forward flow test piping and appurtenance to meet the requirements for 10-2.6 with provision addressed in 5-15.4.6.1*
4. Sprinkler data for Model G XLO is "Bulletin 129E". This is not a current data submittal for this manufacturers sprinkler head. Package must include the current data submittals of sprinkler heads installing.
5. Provide location of required flexible couplings for mains addressed NFPA 13:6-4.2. (NFPA 13:8-1.1.1 (39).
6. Copy/File Room #104 would appear to be classified as OH-1 and spacing of sprinkler shall reflect minimum spacing of the same requirement.
7. Provide and identify an approved relief valve, set to operate at a maximum 175 psi on the riser. (NFPA 13:4-1.2)
8. Provide and identify an inspectors test in this facility.
Miscellaneous action  12/9/2002 DONE
Plans to be returned to submiter for resubmittals of meeting minimum code.
Plan resubmittals received  11/26/2002 DONE
DetailsBill Alexander
Miscellaneous action  11/14/2002 DONE
Received a call from Brodie indicating he wants to put a hold on this plan review untill further notice!
Sprinkler Plan Check11/7/2002 11/14/2002 CANC
DetailsBill Alexander
On hold per Brodie Stenquest telephone call, 11/14/02, 10:00am. New plans coming.
Application received  11/7/2002