INSP-Conference | 3/16/2010 | 3/17/2010 | 3/17/2010 | P | DONE |
Forrest France
|
|
|
Permit expired- see scope of work completed for subsequent permits at this building.
|
DOC - Permit Expired | | | 3/17/2010 | | DONE |
Tisha Gallop
|
|
|
permit expired per Forrest France
|
FIR-Aging Inspection | 3/15/2010 | 3/15/2010 | 3/16/2010 | A | DONE |
Forrest France
|
|
|
See FIR07-00737 for same scope of overhead work completed- permit okay to expire.
|
Miscellaneous action | | | 3/12/2010 | | DONE |
|
|
|
Asked inspector to visit site
|
INSP-Sprinkler Rough-in | 12/11/2002 | 12/11/2002 | 12/11/2002 | P | PART |
Rick Jackson
|
|
|
UNDERGROUND COVER ###-#### CALL FIRST okay to cover; recoated the rods, etc with mastic; will need info on TJI hanger infor per manufacturers listing 12/11/2002 4:10:34 PM
|
INSP-Sprinkler Rough-in | 12/10/2002 | 12/10/2002 | 12/10/2002 | P | NR |
Rick Jackson
|
|
|
CALL BRUCE FIRST; Phone #: ###-#### Internet Inspection Request from: Rita DeYoung not ready; will reschedule 12/10/2002 4:08:32 PM
|
Issue and Print Permit | | | 12/4/2002 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/2/2002 | | 12/2/2002 | | DONE |
|
|
|
|
Telephone call | | | 12/2/2002 | | DONE |
|
|
|
permit ready and fees due
|
Sprinkler Plan Check | 11/27/2002 | | 12/2/2002 | | PASS |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 11/22/2002 | | 11/27/2002 | | FAIL |
Bill Alexander
|
|
|
Calculations have one sprinkler calced? Nodes don't correlate.
|
Miscellaneous action | | | 11/27/2002 | | DONE |
|
|
|
Returned submittal package to submitter for corrections.
|
Plan resubmittals received | | | 11/27/2002 | | DONE |
Bill Alexander
|
|
|
Calculations.
|
Plan resubmittals received | | | 11/22/2002 | | DONE |
|
|
|
To Bill A.
|
Sprinkler Plan Check | 11/13/2002 | | 11/21/2002 | | FAIL |
Bill Alexander
|
|
|
a. Water supply certificate is not on the same block as permitted work shown. Fire sprinkler contractor shall provide a current water supply certification for this system, addressed at point of connection.
b. Provide addressing and clarification of required forward flow testing of backflow preventer meeting 5-15.4.6.1 with accommodations for 10-2.6.
c. Provide detailed loads of pipe and zones being braced with correlation of earthquake details and locations. NFPA 13:8-1.1.1 (39)
d. Provide and show on the plans the required inspectors test. NFPA 13:8-1.1.1 (23)
e. Plans must include thrust-restraining requirements of the underground and how this contractor intends to suppress it meeting NFPA 13/24.
f. Provide an auxiliary drain (w/signage) for this system at the riser, since this system will not drain outside.
g. Provide the formula derived incorporating 7-2.3.2.4 on the plans.
h. Provide calculation node points on "Riser Detail" section, corresponding to calculations.
i. Provide hanger location for the mains.
|
Miscellaneous action | | | 11/21/2002 | | DONE |
|
|
|
Took failed plans to front desk for calling and returning for corrections.
|
Application received | | | 11/13/2002 | | |
|
|
|
|
Plan assigned to (Bill) | 11/13/2002 | | | | |
|
|
|
|
Case Summary | | | | | DONE |
|
|
|
|