Permit Number | FIR02-00506 |
Status | Finaled |
Name |
SIMPLEX/GRINNELL
|
Site Address |
3201 W AIRPORT WAY
|
Project Name | alm-AIRPORT |
Customer Number | |
ePlanReview | |
Description |
BOISE AIR TERMINAL - CONCOURSE B EXPANSION - AIRCRAFT LOADING WALKWAY - To add a smoke detector and magnetic door hold-open on the concourse side of the new doorway entrance to a new aircraft-loading ramp to be connected to the existing airport fire alarm system. No changes to battery supply required.
The associated building permit BLD02-02367 is to construct a new entrance vestibule and support structure to serve a new aircraft loading walkway at "Concourse B Expansion". Work is to include a concrete foundation, cantilevered beams, concrete floor deck, spray applied fireproofing, steel roof deck, and equipment all per approved drawings, engineering, and plan review conditions on file. The 2nd floor level shall be maintained as a 1-hr occupancy separation. The new aircraft loading walkway shall comply with NFPA 415.
|