Final inspection | | | 11/28/2007 | | PASS |
|
|
|
This entry was made to final this fire alarm permit that passed 4/23/2003 by Rick Jackson
|
Telephone call | | | 7/30/2003 | | DONE |
|
|
|
Tecon from Mike Timmerman, M2 Automation, re adding additional detectors to release 3 FSD's in basement. These were not shown on original plans but they can be added as a plan modification to this open permit to facilitate adding these to the new system. Keep this permit open until plans have been received, approved and finaled by field inspection for these smoke damper detectors. Sam.
|
INSP-Alarm Testing | 4/22/2003 | 4/23/2003 | 4/23/2003 | A | PASS |
Rick Jackson
|
|
|
Rick, This is to test the lobby between building #1 & #2. Also Horn Strobes added on 3rd floor and 2nd floor walkways. I will not be there, but Jason & Bob will. As we talked in the parking garage yesterday we can be there very early. 7:00 am if you would like. Please call me ###-#### on the time.
Thanks Mike; Phone #: ###-#### Internet Inspection Request from: Mike Timmerman tested new horn/strobes in walkways and lobby 4/23/2003 2:48:19 PM
|
INSP-Alarm Testing | 2/21/2003 | 2/24/2003 | 2/24/2003 | A | PART |
Rick Jackson
|
|
|
###-####- or cell ###-####-- mike temp occ approved per Dave Miller; need notification in walkways on 2 and 3 floor and 1st floor lobby; need alaternate floor recall for elevator; need update maps and device descriptors; 2/24/2003 10:18:11 AM
|
Issue permit | | | 2/19/2003 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/14/2003 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/14/2003 | | 2/14/2003 | | DONE |
|
|
|
|
Telephone call | | | 2/14/2003 | | DONE |
|
|
|
permit ready
|
Plan assigned to (SAM) | 12/24/2002 | | 2/14/2003 | | DONE |
|
|
|
2/14/2003 10:35:46 SLR - activity updated through activity FIRA22 from case FIR02-00515.
|
Plan resubmittals received | | | 2/13/2003 | | DONE |
|
|
|
|
Alarm Plan Check | | | 2/13/2003 | | PASS |
|
|
|
|
Alarm Plan Check | | | 1/14/2003 | | FAIL |
|
|
|
Conditional approval granted to begin installation. Final inspection shall not be made until approved plans and permit is issued. Review comments discussed with and faxed to Mike at M2 Automation.
|
Application received | | | 12/24/2002 | | |
|
|
|
|