INSP-Final Inspection | 10/31/2003 | 10/31/2003 | 10/31/2003 | A | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 10/31/2003 | 10/31/2003 | 10/31/2003 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 10/31/2003 8:17:55 AM
|
INSP-Sprinkler Rough-in/Hydro | 9/2/2003 | 9/2/2003 | 9/2/2003 | P | PART |
Troy Cobbley
|
|
|
provide as-builts to the city of boise showing the new hose vavle locations, provide EQ bracing on the 4" piping in the locations as discussed, provide signage for the stand pipe per review notes, provide verification that there is adequate clearance for hose hookup at the top north hose vavle with the fire dept. Hydro test is OK 9/2/2003 3:04:21 PM 9/2/2003 3:08:33 PM
|
Miscellaneous action | | | 8/14/2003 | | DONE |
|
|
|
Received a fax on a hose stations being relocated due to problems mounting them to column assemblies. Responded that it has to meet the requirements of NFPA 14:5-3.2, and denied the request.
|
INSP-Conference | 8/7/2003 | 8/11/2003 | 8/11/2003 | A | DONE |
Troy Cobbley
|
|
|
The sprinkler contractor is requesting the relocation of the hose valves at the south end of the project. It appears the hose vavles will still meet NFPA 14 spacing requirements but they will need to contact Bill Alexander for final approval and resubmit an as-built before final approval 8/11/2003 11:01:45 AM
|
INSP-Conference | 6/26/2003 | 6/26/2003 | 6/26/2003 | P | DONE |
Troy Cobbley
|
|
|
mike; Phone #: ###-#### Hose valves relocated and elevation changed. This is for the two vavles located in the egress path. OK per Bill Alexander and I. 6/26/2003 4:17:22 PM
|
Issue and Print Permit | | | 3/21/2003 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 1/6/2003 | | 3/20/2003 | | DONE |
|
|
|
3/20/2003 14:04:45 JWA - activity updated through activity FIRA22 from case FIR03-00006.
|
Sprinkler Plan Check | 3/14/2003 | | 3/20/2003 | | PART |
Bill Alexander
|
|
|
Requires earthquake resubmittals.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2003 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 3/20/2003 | | 3/20/2003 | | DONE |
|
|
|
|
Telephone call | | | 3/20/2003 | | DONE |
|
|
|
permit ready
|
Plan assigned to (Bill) | 3/14/2003 | | 3/14/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/14/2003 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/6/2003 | | 1/22/2003 | | FAIL |
Bill Alexander
|
|
|
1. The feed/supply main is shown as buried underneath this structures floor. Pipe shall not be run under buildings. Exception: When absolutely necessary to run pipe under buildings, special precautions shall be taken that include arching the foundation walls over the pipe, running pipe in covered trenches, and providing valves to isolate sections of pipe under buildings. (NFPA 14:4-1.2.6)
2. Provide clarification of the 2" C900 PVC piped for the sump drain line. Provide data submittal of that piping, its' drain valve, etc. Pipe or tube used in standpipe systems shall meet or exceed one of the standards in NFPA 14 Table 2-2.1 or shall be in accordance with 2-2.2 through 2-2.6. (NFPA 14:2-2.1)
3. Provide better detail on a standpipe riser/s, which includes dimensioned elevation view of the structure, the dimensioning elevation of those devices/connections, dimensioning location of required flexible connections in contrast to floor penetrations, support clamps, bracing, etc, all meeting minimum requirements of NFPA 14:6-1.
4. Provide location of the hydrants which shall be used for this facility on the "Site Plan." (NFPA 14:6-1)
5. When the installation of sprinkler heads is not involved or insignificant due to the type of work being permitted, a plan review fee equivalent to 1.05% of the total bid price shall be assessed, up to a maximum of $3,150.00 or a minimum of $105.00 (whichever is larger), and paid to the Building Official. Provide your contract price for this work in order to verify permit fee requirements meeting BCO ยง4-02-28(2-B)
|
Miscellaneous action | | | 1/22/2003 | | DONE |
|
|
|
Returned plans to the front desk for calling and returning denied plans - 3:15 pm.
|
Telephone call | | | 1/22/2003 | | DONE |
|
|
|
plans failed called for pickup
|
Application received | | | 1/6/2003 | | |
|
|
|
|