INSP-Final Inspection | 2/3/2005 | 2/4/2005 | 2/4/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm finally finaled! 2/4/2005 11:02:58 AM
|
DOC - Permit Finaled | 2/4/2005 | 2/4/2005 | 2/4/2005 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 2/4/2005 11:03:03 AM
|
INSP-Final Inspection | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was to verify that the waterflow switch is still intermittent as far as timing. It appears that the water for the sprinkler system is surging which won't allow the flow switch to activate. I left correction notice with Mountain Alarm and Eric with Red Cross 1/27/2005 8:17:47 AM
|
INSP-Final Inspection | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | NR |
Rick Jackson
|
|
|
linda; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Talked to Linda and the flow switch problem has been turned over to Viking 1/27/2005 8:15:50 AM
|
Issue permit | | | 1/26/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 1/10/2005 | | PASS |
|
|
|
Plan Modification (as-built drawings). Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/10/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/10/2005 | | 1/10/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/7/2005 | 1/7/2005 | 1/7/2005 | P | FAIL |
Troy Cobbley
|
|
|
Bells still did not ring within 90 seconds 1/7/2005 2:29:29 PM
|
INSP-Final Inspection | 1/5/2005 | 1/6/2005 | 1/6/2005 | P | FAIL |
Troy Cobbley
|
|
|
Waterflow did not come into panel within 90 seconds 1/6/2005 1:11:38 PM
|
Plan resubmittals received | | | 1/5/2005 | | |
|
|
|
|
INSP-Final Inspection | 12/16/2004 | 12/17/2004 | 12/17/2004 | P | FAIL |
Troy Cobbley
|
|
|
Need two a/v's relocated to within 15' of the end of the corridor on the third floor and in the basement. Replace the door holder on the first floor and provide as builts. 12/17/2004 1:49:24 PM
|
INSP-Alarm Testing | 12/14/2004 | 12/15/2004 | 12/15/2004 | P | FAIL |
Troy Cobbley
|
|
|
See correction notice and approved plans for items needing attention 12/15/2004 4:13:09 PM
|
Inspection Record Card- Fire | 12/14/2004 | | 12/14/2004 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/14/2004 | | DONE |
|
|
|
has been in before
|
Alarm Plan Check | | | 12/14/2004 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2004 | | DONE |
|
|
|
|
(F) Reprint permit | | | 12/14/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/10/2004 | | |
|
|
|
|
INSP-Alarm Testing | 12/7/2004 | 12/8/2004 | 12/8/2004 | A | FAIL |
Troy Cobbley
|
|
|
Inspection stopped after testing initiating devices on the first and second floors. Third floor not looked at. Elevator recall and sprinkler flow not done nor duct detectors on the roof. Monitoring company did not receive trouble for loss of phone lines, a/c power or loss of batteries. Resubmittals required. See city approved plans for specific locations and deficiencies. 12/8/2004 2:58:42 PM
|
Issue and Print Permit | | | 11/4/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 11/3/2004 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2004 | | DONE |
|
|
|
|
Miscellaneous action | | | 11/3/2004 | | DONE |
|
|
|
Faxed comments to Eric Beasley (Red Cross)
|
Permit Ready to Issue | | | 11/3/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/3/2004 | | 11/3/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/28/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 10/22/2004 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Lynde Jones, Mt Alarm
|
Telephone call | | | 10/22/2004 | | DONE |
|
|
|
I called Lynde to go over the comments. I requested she come down and we will review comments and compare plans.
|
Telephone call | | | 10/22/2004 | | DONE |
|
|
|
I called Derald Watts, owner's rep. to advise him of the status of this permit and express our concern at the time it is taking to get the alarm system up to code. He was appreciative and unaware of the history. Reviewed activity log with him. He indicated contracts associated with the original bldg permit were handled by corporate. He will follow up with them on how to proceed on finding a way to expedite this work to satisfactory completion.
|
Plan resubmittals received | | | 10/15/2004 | | |
|
|
|
|
INSP-Alarm Testing | 8/3/2004 | 8/4/2004 | 8/4/2004 | P | FAIL |
Troy Cobbley
|
|
|
Provide resubmittals showing the correct wiring for initiating zones and show door hold opens. Provide "Request to Exit" buttons per IFC 1003.3.1.3.4. See review notes. Provide correct count of horns. Provide verification of note #9. Need to retest pull stations and fire sprinkler items and horns on second floor. A re-inspection fee will apply upon the next inspection. 8/4/2004 4:25:07 PM
|
Issue and Print Permit | | | 8/2/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/30/2004 | | 7/30/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/30/2004 | | DONE |
|
|
|
Spoke with caholly and told her that permit is ready & fees///7/30/04 2:30pm BAM
|
Alarm Plan Check | | | 7/30/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/30/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/29/2004 | | |
|
|
|
|
Alarm Plan Check | | | 7/9/2004 | | FAIL |
|
|
|
Resubmittal required. Brent stated there are door hold-opens within the building, they are not included on the plans or riser.
|
Telephone call | | | 7/9/2004 | | DONE |
|
|
|
Called Rob Bailey (Mt Alarm), (Brent and Lynde were out today) to request cut sheets for the magnetic lock relay and a revised battery calculation.
|
Plan resubmittals received | | | 7/2/2004 | | |
|
|
|
|
Alarm Plan Check | | | 6/18/2004 | | FAIL |
|
|
|
Resubmittal required. Phone call to Lynde Jones at Mt Alarm. The security devices were not shown on the plans that were resubmitted, the responsible party has left for the day and will have him call to make an appointment on Monday.
|
Plan resubmittals received | | | 6/17/2004 | | |
|
|
|
|
Telephone call | | | 6/15/2004 | | DONE |
|
|
|
Spoke with Lynde Jones at Mt Alarm. She will track down the drawings and ensure they are resubmitted no later than tomorrow.
|
Telephone call | | | 5/27/2004 | | DONE |
|
|
|
HOLD. Brent from Mt Alarm, the floor plans that have been submitted do not show the correct doors and locations. They will resubmit plans with the proper door layout.
|
Telephone call | | | 5/18/2004 | | DONE |
|
|
|
I spoke with Linde Jones, she was unsure of the exact nature of the resubmittal, except she was told to add relays to the FACP to deactivate the security doors. I explained that we require the security hardware shown on the affected doors on the plans so our inspector know which and how many doors to test. I stated that I would accept these plans if someone marked them up to reflect the security hardware and locations. She will have Brent call me and we will determine the additional information required to pass the Plan Modification to the original permit.
|
Plan resubmittals received | | | 5/4/2004 | | DONE |
|
|
|
|
INSP-Final Inspection | 3/19/2004 | 3/19/2004 | 3/19/2004 | P | FAIL |
Troy Cobbley
|
|
|
Plans need to be resubmitted showing the new door magnet/security interface. Items tested today are both phone lines, vavle tamper switch and battery calculations which are ok. The smoke detector is now approved to be used with this panel. 3/19/2004 4:34:10 PM
|
INSP-Final Inspection | 6/4/2003 | 6/6/2003 | 6/6/2003 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 6/4/2003 at 9:39:28 AM. Contact: ###-####. started to test sprinkler flow but couldn't locate inspectors test (after checking the exterior it appears to be on the northwest side of the building); need compatibility for smoke above panel; this is all that was done for today; they will reschedule for 6/9/03 to finish 6/6/2003 5:07:43 PM
|
INSP-Final Inspection | 3/18/2003 | 3/19/2003 | 3/19/2003 | P | FAIL |
Troy Cobbley
|
|
|
provide the correct smoke detector as per the submittals, verify a dedicated circuit, provide map, verify battery standby once the dedicated circuit is found, provide sign on door, test all initiating devices and verify signals 3/19/2003 4:14:10 PM
|
INSP-Final Inspection | 2/19/2003 | 2/21/2003 | 2/21/2003 | P | CANC |
Troy Cobbley
|
|
|
nicole ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie--cancel per pam
|
Inspection Record Card- Fire | 1/27/2003 | | 1/27/2003 | | DONE |
|
|
|
|
Telephone call | | | 1/27/2003 | | DONE |
|
|
|
permit ready and fees due
|
Issue permit | | | 1/27/2003 | | DONE |
|
|
|
|
Alarm Plan Check | | | 1/24/2003 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/24/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 1/10/2003 | | 1/24/2003 | | DONE |
|
|
|
1/24/2003 17:58:17 SLR - activity updated through activity FIRA22 from case FIR03-00012.
|
Plan resubmittals received | | | 1/16/2003 | | DONE |
|
|
|
|
Application received | | | 1/10/2003 | | |
|
|
|
|
Alarm Plan Check | | | 1/14/2002 | | FAIL |
|
|
|
faxed Mountain alarm the application with missing items circled for resubmittal
|
Inspection Record Card- Fire | 7/30/2004 | | | | |
|
|
|
|
Inspection Record Card- Fire | 12/14/2004 | | | | |
|
|
|
|