INSP-Final Inspection | 2/24/2004 | 2/24/2004 | 2/24/2004 | P | PASS |
Rick Jackson
|
|
|
We would like a final this PM. Please call prior to arrival.; Phone #: ###-#### Internet Inspection Request from: Trent Bice
|
DOC - Permit Finaled | 2/24/2004 | 2/24/2004 | 2/24/2004 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 2/24/2004 4:30:12 PM
|
Sprinkler Plan Check | 11/4/2003 | | 2/20/2004 | | PASS |
Bill Alexander
|
|
|
11/4/03 - Plan correction/changes, connection of basement standpipe piping from PA-2 and PA-1, addition of PRV for fire pump.
Problem with resubmittals. Called Don Weland and asked for more information, i.e., data submittals on PRV, verification of hydraulics that 175 psi maximum pump pressure will be sufficiant for most remote/demanding area calculations.
02/20/04 - PRV's not required due to system testing. Standpipe connection piping provided to column line #13.
NOTE: Other changes submitted under FIR03-00088, then to this permit and now forwarded onto FIR03-00136 relating to the 6th floor concealed space under the elevator mechanical room #2.
|
Plan assigned to (Bill) | 11/4/2004 | | 2/20/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/20/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/20/2004 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/20/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/4/2003 | | |
Bill Alexander
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 9/23/2003 | 9/24/2003 | 9/24/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/23/2003 at 1:55:32 PM. Contact: ###-####. hydro okay 9/24/2003 12:22:48 PM
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2003 | 9/23/2003 | 9/23/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 9/22/2003 at 2:25:13 PM. Contact: ###-####. hydro okay on systems one and two 9/23/2003 1:09:00 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/30/2003 | 7/31/2003 | 7/31/2003 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 7/30/2003 at 11:50:58 AM. Contact: ###-####. installed per resubmittals 7/31/2003 3:10:36 PM
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2003 | 7/30/2003 | 7/30/2003 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 7/29/2003 at 9:59:04 AM. Contact: ###-####. rescheduled for 7/31 7/30/2003 11:35:03 AM
|
Telephone call | | | 7/22/2003 | | DONE |
|
|
|
permit ready and fees due
|
Sprinkler Plan Check | 7/10/2003 | | 7/21/2003 | | PASS |
Bill Alexander
|
|
|
Field Changes/modifications.
|
Plan resubmittals received | | | 7/10/2003 | | |
|
|
|
|
Miscellaneous action | | | 7/9/2003 | | DONE |
|
|
|
Received a modification for the basement system #3, which probably will affect the capacity of the system to exceed 750 gallons. Responded with letter, attached to permit. Copied Rick Jackson (email and mail box).
|
INSP-Sprinkler Rough-in/Hydro | 7/7/2003 | 7/8/2003 | 7/8/2003 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 7/7/2003 at 2:36:20 PM. Contact: ###-####. resubmittals needed for pipe changes and relocation of inspectors tests; may put systems over 750 gallons; Scheduled by a contractor via Hello! on 7/7/2003 at 2:34:48 PM. Contact: ###-####. need resubmittals for pipe changes and standpipe changes; need listing for fire stopping standpipe through floor/ceiling assembly; EQ needed; need heat to maintain 40 degrees in north rooms where main enters building through vestibule and bike room 7/8/2003 4:25:20 PM
|
FIR-Aging Inspection | 6/16/2003 | 6/16/2003 | 6/16/2003 | | PART |
Rick Jackson
|
|
|
work is still in progress 6/16/2003 9:48:08 AM
|
Issue permit | | | 3/13/2003 | | |
|
|
|
|
Sprinkler Plan Check | 3/3/2003 | | 3/12/2003 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/12/2003 | | DONE |
Bill Alexander
|
|
|
|
Override - Parcel Holds | | | 3/12/2003 | | |
|
|
|
|
Inspection Record Card- Fire | 3/12/2003 | | 3/12/2003 | | DONE |
|
|
|
|
Telephone call | | | 3/12/2003 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 3/3/2003 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/18/2003 | | 2/24/2003 | | FAIL |
Bill Alexander
|
|
|
1. Exceeding permitted work in association with building permit.
2. Compressor/components are not listed for fire service.
3. Forward flow test for double check lacks detail/calculation verification.
4. Provisions for basement system drains are insufficient or lacking.
5. Water supply certificate is not on the correct addressed street for as providing tap.
6. Dry standpipe requires signage - to be addressed on the plans.
7. Earthquake zones, corresponding bracing is not shown or coordinated on the plans.
8. Several incorrect interpretations given in earthquake plan notes for bracing types/locations.
|
Miscellaneous action | | | 2/24/2003 | | DONE |
|
|
|
Took failed plans to front desk for returning and corrections.
|
Telephone call | | | 2/24/2003 | | DONE |
|
|
|
Faxed copy of review to Shilo A.S.
|
Telephone call | | | 2/24/2003 | | DONE |
|
|
|
plans failed called for pick up
|
Plan assigned to (Bill) | 2/18/2003 | | 2/20/2003 | | DONE |
|
|
|
2/20/2003 10:46:39 JWA - activity updated through activity FIRA22 from case FIR03-00069.
|
Application received | | | 2/18/2003 | | |
|
|
|
|