Permit Information
Permit NumberFIR03-00079
StatusFinaled
Name MK PLAZA 1 (SMOKE-CONTROL)
Site Address 400 S BROADWAY AVE
Project Namealm-MK PLAZA I
Customer Number 
ePlanReview 
Description
MK PLAZA 1 (SMOKE-CONTROL) - To install a Fire Department/Building Dept conceptually-approved smoke management system, designed by Michael Dillon, Professional Engineer. The return air duct smoke detection system is designed to automatically close all fire/smoke dampers and doors, and shut down all air handlers. Also a manual control system is provided for Fire Department use for smoke removal/control. The system will be connected to the existing building fire alarm system for "fire alarm" annunciation (notification) and offsite monitoring purposes.
The associated building permit (BLD 02-02584) is to construct or upgrade passive smoke barriers throughout an existing 111,000 square foot building having 6 stories and a basement. The work shall be compatible with a report prepared by Michael E. Dillon, Professional Engineer, and approved by the Boise City Building Division. A non-essential (i.e. non-life-safety) mechanical smoke management system is also proposed. Work is to include smoke dampers, fire dampers, combination fire and smoke dampers, smoke doors, and smoke control at the elevator doors on the 4th floor. A smoke control panel will be provided to operate the non-essential smoke management system. The system will be manual operable only and is NOT required to comply with 1997 UBC Section 905. This building is fire sprinklered to mitigate the potential hazards of the atrium. The fire sprinkler system shall be maintained in compliance with NFPA 13 as regulated by the Fire Department.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/1/20038/4/20038/4/2003APASS
DetailsRick Jackson
tony ###-####
DOC - Permit Finaled8/4/20038/4/20038/4/2003PPASS
DetailsRick Jackson
Finaled by inspector at 8/4/2003 12:13:01 PM
INSP-Final Inspection7/28/20037/28/20037/28/2003PFAIL
DetailsRick Jackson
need smoke above panel; replace ceiling in FACP room 7/29/2003 7:34:14 AM
FIR-Aging Inspection7/2/20037/2/20037/2/2003 PASS
DetailsRick Jackson
work is still in progress 7/2/2003 10:16:44 AM
Inspection Record Card- Fire4/2/2003 4/2/2003 DONE
Telephone call  4/2/2003 DONE
Issue and Print Permit  4/2/2003 DONE
Plan assigned to (SAM)2/24/2003 4/1/2003 DONE
4/1/2003 16:21:43 SLR - activity updated through activity FIRA22 from case FIR03-00079.
PLANS/APPL TAKEN TO FRONT DESK  4/1/2003 DONE
Plan resubmittals received  4/1/2003 DONE
2nd set of cut sheets received today. Plans now ready to issue.
Alarm Plan Check  3/31/2003 PASS
Telephone call  3/31/2003 DONE
Called Hobson requesting second set of cut sheets necessary to attach to field set of plans. HOLD approved plans pending receipt of this cut sheet set.
Plan resubmittals received  3/19/2003 DONE
received fax of required plan revisions.
Meeting  3/7/2003 DONE
Met with reps to discuss plans. System functional questions resolved. Several minor plan discrepancies noted such as ommissions, address discrepancies, etc will be corrected and field verified. Need to replace the matrix on sheet FA3.1 if a clearly written instruction sheet; necessary to ensure proper operator and FD personnell emergency response. Will fax this revised sheet before plans are approved.
Alarm Plan Check  3/5/2003 FAIL
Plans lack sufficient details and explanation for approval. Meeting set up to discuss.
3/7/03 - HOLD plan review for receipt of a revised operating matrix and FD operating instructions.
Application received  2/24/2003