INSP-Final Inspection | 7/14/2010 | 7/14/2010 | 7/14/2010 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. The pendant spacing in the coolers has been corrected.
|
INSP-Conference | 5/14/2010 | 5/17/2010 | 5/18/2010 | P | DONE |
Troy Cobbley
|
|
|
Per phone conversation with George this project is being taken care of.
|
INSP-Conference | 5/11/2010 | 5/14/2010 | 5/14/2010 | A | DONE |
Troy Cobbley
|
|
|
I left messages on Ron's and Jeff's voice mails requesting status of project. Follow up inspection at walmart scheduled for monday.
|
FIR-Aging Inspection | 5/5/2010 | 5/5/2010 | 5/11/2010 | | NR |
Troy Cobbley
|
|
|
I spoke to jeff and ron about job status. They will let me know by friday. Follow inspection has been scheduled.
|
Miscellaneous action | | | 3/12/2010 | | DONE |
|
|
|
Sent email requesting project status. Please, see below.
The above permit is still open and is in the issued status. What is the disposition of this project? The last activity was reported on 03-08-10 "Information forwarded to Scott for further action with nonreponsive contractor."
This was only a couple days ago, so I am assuming you have not made any progress. When you have some news please let me know
Tim
|
FIR-Aging Inspection | 3/4/2010 | 3/4/2010 | 3/8/2010 | | NR |
Troy Cobbley
|
|
|
Information forwarded to Scott for further action with nonreponsive contractor.
|
INSP-Conference | 8/8/2008 | 8/8/2008 | 8/8/2008 | P | DONE |
Troy Cobbley
|
|
|
I spoke to greg and he was going to follow up on getting this permit finaled. He was going on vacation and would get back to me.
|
FIR-Aging Inspection | 9/26/2005 | 9/26/2005 | 9/26/2005 | | DONE |
Troy Cobbley
|
|
|
I spoke to Jeff Packam and he stated that the job status would be investigated fully and the situation rectified.
|
FIR-Aging Inspection | 7/1/2005 | 7/1/2005 | 7/1/2005 | | DONE |
Troy Cobbley
|
|
|
I left message at answering service for Jeff Packam for job status
|
INSP-Sprinkler Rough-in | 5/19/2003 | 5/19/2003 | 5/19/2003 | P | FAIL |
Troy Cobbley
|
|
|
dry pendants are over spaced in the coolers and freezers as marked on the job site approved plans. Max. head spacing to be 130 sq. ft. per approved plans 5/19/2003 5:30:00 PM
|
Plan assigned to (Bill) | 2/26/2003 | | 3/7/2003 | | DONE |
|
|
|
3/7/2003 10:07:28 JWA - activity updated through activity FIRA22 from case FIR03-00082.
|
Sprinkler Plan Check | 2/26/2003 | | 3/7/2003 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/7/2003 | | DONE |
Bill Alexander
|
|
|
|
Inspection Record Card- Fire | 3/7/2003 | | 3/7/2003 | | DONE |
|
|
|
|
Telephone call | | | 3/7/2003 | | DONE |
|
|
|
permit ready
|
Issue permit | | | 3/7/2003 | | DONE |
|
|
|
|
Application received | | | 2/26/2003 | | |
|
|
|
|