Permit Information
Permit NumberFIR03-00133
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 4477 W WILLOW LN
Project NameSPR WOMENS & CHILDREN ALLIANCE
Customer Number 
ePlanReview 
Description
Women's and Children's Alliance * To install a new fire sprinkler system in a, 11,000-ft/2, type (a)VB, I1 and I4 occupancy structure. The structure is also getting some remodel, which includes the kitchen, and some bedrooms. This permit includes the underground, starting at the property line in N. Willow Lane, traveling east and north, approximately 292'-0" of 6" C-900 PVC, into a mechanical room. The fire sprinkler system work shall be installed in accordance to NFPA 13-1999, complying with the IFC-2000 and attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD03-00334.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/19/20039/19/20039/19/2003PPASS
DetailsTroy Cobbley
DOC - Permit Finaled9/19/20039/19/20039/19/2003PPASS
DetailsTroy Cobbley
Finaled by inspector at 9/19/2003 1:00:45 PM
INSP-Sprinkler Rough-in/Hydro9/8/20039/9/20039/9/2003APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 9/8/2003 at 2:56:05 PM. Contact: ###-####. hydro on overhead okay 9/9/2003 11:13:33 AM
INSP-Supply line flush9/5/20039/8/20039/8/2003APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 9/5/2003 at 1:24:30 PM. Contact: ###-####. UG hydro okay; will give ther UG certificate to Troy 9/8/2003 11:08:56 AM
INSP-Sprinkler Rough-in9/4/20039/4/20039/4/2003PFAIL
DetailsTroy Cobbley
see approved plans for deficiancy locations 9/4/2003 3:39:12 PM
INSP-Supply line flush7/21/20037/22/20037/22/2003APASS
DetailsTroy Cobbley
supply line flush ok 7/22/2003 8:17:31 AM
INSP-Supply line flush7/18/20037/21/20037/21/2003AFAIL
DetailsTroy Cobbley
Inspection was for rough-in on north wing. See approved plans for areas with deficiencies. 7/21/2003 10:26:55 AM
INSP-Sprinkler Rough-in/Hydro7/17/20037/18/20037/18/2003PFAIL
DetailsTroy Cobbley
Rough-in inspection performed on the east, west and south wings. North wing still needs to be done. Separation between the east wing and the living area is an issue. Earthquake bracing needs to be moved to the top chord of the trusses or get engineering sign off. Extended coverage sidewalls not installed. 7/18/2003 2:03:02 PM
INSP-Supply line flush6/24/20036/25/20036/25/2003PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 6/24/2003 at 4:00:39 PM. Contact: ###-####. not a flush; thrust block at base of riser okay; pictures of UG not developed yet 6/25/2003 2:19:25 PM
INSP-Supply line flush6/20/20036/23/20036/23/2003ACANC
DetailsTroy Cobbley
Debest will call when the thrust blocks are ready for inspection. Due to high water table pipe will be buried as it is installed and pictures will be taken and shown to the inspector before sign off 6/23/2003 2:25:25 PM
Telephone call  5/30/2003 DONE
left mess that permit is ready
Issue permit  5/30/2003  
Plan assigned to (Bill)3/20/2003 5/29/2003 DONE
5/29/2003 13:05:12 JWA - activity updated through activity FIRA22 from case FIR03-00133.
Sprinkler Plan Check5/27/2003 5/29/2003 PASS
DetailsBill Alexander
Possible recalculation required for slope exceeding 2" in 12" with condition of a attic wall?
PLANS/APPL TAKEN TO FRONT DESK  5/29/2003 DONE
DetailsBill Alexander
Inspection Record Card- Fire5/29/2003 5/29/2003 DONE
Inspection Record Card- Fire5/29/2003 5/29/2003 DONE
Plan resubmittals received  5/27/2003 DONE
Sprinkler Plan Check3/20/2003 4/16/2003 FAIL
DetailsBill Alexander
03/31/03 - Waiting for IBC and IFC reviews to be accomplished.

Plan review failed due to spacing coverage and lack of details to verify protection coverage.
Miscellaneous action  4/16/2003 DONE
Took plans to front desk for calling and returning.
Telephone call  4/16/2003 DONE
PLANS FAILED CALLLED TO LET DEBEST KNOW
Miscellaneous action  3/31/2003 DONE
Emailed Contractor that the IBC and IFC have not been completed and cannot do fire protection reviews until these have been accomplished.
Application received  3/20/2003