Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR03-00186
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1318 N MAPLE GROVE RD
Project NameSPR LITHIA AUTO BODY
Customer Number 
ePlanReview 
Description
To install a complete (gridded - overhead), wet pipe, fire sprinkler system in a new 23,710 ft/2, one story, auto body repair shop with related office and storage areas. The building is constructed on a pre-engineered metal building frame with masonry and steel stud exterior walls. All fire sprinkler system work shall be in accordance to NFPA 13-1999, complying with the 1997 - UFC and attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The underground fire service main was installed under FIR03-00134. This permit is attached to Building Permit: BLD03-00186.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Conference7/17/20037/18/20037/18/2003APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 7/17/2003 at 4:47:00 PM. Contact: ###-####.
INSP-Final Inspection7/17/20037/18/20037/18/2003APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 7/17/2003 at 4:47:44 PM. Contact: ###-####.
DOC - Permit Finaled7/18/20037/18/20037/18/2003PPASS
DetailsRick Jackson
Finaled by inspector at 7/18/2003 5:15:09 PM
INSP-Final Inspection7/17/20037/18/20037/17/2003PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 7/17/2003 at 4:05:45 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jul 17 2003 4:46PM.
INSP-Conference7/17/20037/18/20037/17/2003PCANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 7/17/2003 at 4:04:53 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Jul 17 2003 4:45PM.
INSP-Sprinkler Rough-in/Hydro7/16/20037/17/20037/17/2003APART
DetailsTroy Cobbley
above ground hydro test is ok. Need test papers. Forward flow flush test is OK. Rough-in for office area is OK except for the combustible concealed spaced created by the mechanical mezzanine. Upright sprinkler heads will need to be added. All shop areas need looked at. 7/17/2003 4:10:51 PM
INSP-Sprinkler Rough-in7/16/20037/16/20037/16/2003PFAIL
DetailsRick Jackson
performed a walk through while doing the UG flush; need approved plans; heads obstructed by soffit in main lobby/counter; heads taped in west bay throughout 7/16/2003 12:56:58 PM
Sprinkler Plan Check5/2/2003 5/15/2003 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  5/15/2003 DONE
DetailsBill Alexander
Inspection Record Card- Fire5/15/2003 5/15/2003 DONE
(F) Reprint permit  5/15/2003  
CHANGE STATUS TO (ISS)  5/15/2003 DONE
ALREADY ISSUED
Plan resubmittals received  5/2/2003  
Resubmittal review of previous denied spray booth, mixing room, etc.
Issue permit  4/30/2003 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/29/2003 DONE
DetailsBill Alexander
Inspection Record Card- Fire4/29/2003 4/29/2003 DONE
Telephone call  4/29/2003 DONE
left mess that permit is ready
Plan assigned to (Bill)4/17/2003 4/28/2003 DONE
4/28/2003 15:44:52 JWA - activity updated through activity FIRA22 from case FIR03-00186.
Sprinkler Plan Check4/17/2003 4/28/2003 PART
DetailsBill Alexander
Requires resubmittal addressing code issues.
Application received  4/17/2003