INSP-Final Inspection | 11/26/2003 | 11/26/2003 | 11/26/2003 | P | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 11/26/2003 | 11/26/2003 | 11/26/2003 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 11/26/2003 12:05:23 PM
|
INSP-Final Inspection | 10/10/2003 | 10/10/2003 | 10/10/2003 | P | PART |
Troy Cobbley
|
|
|
NAC panels had to be replaced due to excessive current draw. Manufacture sent out a temp. replacement panel that still draws more power than original design. New panels will be in within 5 days. The panels installed require 7.6 ah batteries to meet code. 7 ah are installed.
|
INSP-Final Inspection | 10/3/2003 | 10/6/2003 | 10/6/2003 | A | FAIL |
Troy Cobbley
|
|
|
alarm contractor was not able to make inspection 10/6/2003 2:52:30 PM
|
INSP-Final Inspection | 9/30/2003 | 9/30/2003 | 9/30/2003 | P | CANC |
Troy Cobbley
|
|
|
wrong inspection called in 9/30/2003 3:49:44 PM
|
Issue and Print Permit | | | 9/23/2003 | | DONE |
|
|
|
|
Alarm Plan Check | | | 9/22/2003 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/17/2003 | | DONE |
|
|
|
Resubmitual received: Fax from Protex that contains a letter from Silent Knight that states the pull station PS-DA can be used with a plastic cover to divert moisture. Temperature is not a factor.
|
Plan resubmittals received | | | 9/11/2003 | | DONE |
|
|
|
|
Issue permit | | | 9/4/2003 | | |
|
|
|
|
Alarm Plan Check | | | 9/3/2003 | | PASS |
|
|
|
Resubmittal required on item #14, UL listing on pull station for outside usage with cover, prior to a final on the fire alarm system. All other items are approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/2003 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/3/2003 | | 9/3/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/3/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/3/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 5/28/2003 | | 9/3/2003 | | DONE |
|
|
|
9/3/2003 11:15:59 M_F - activity updated through activity FIRA22 from case FIR03-00277.
|
Plan resubmittals received | | | 8/14/2003 | | DONE |
|
|
|
|
Telephone call | | | 8/7/2003 | | |
|
|
|
Called Rob Ahten to notify him that the drawings that he submitted are not clouded as he stated. I requested that he re-submit with 2 complete sets as required. He stated he would.
|
Plan resubmittals received | | | 8/5/2003 | | |
|
|
|
|
Telephone call | | | 7/29/2003 | | |
|
|
|
Called to remind Rob that he was to stop by and "cloud" the changes on the Aspen Springs Apartment resubmittal (he agreed to do so 7/17/2003). Left a message.
|
Telephone call | | | 7/17/2003 | | |
|
|
|
Phoned Rob Ahten at Protex to request that he "cloud" his changes from the previous submittal per the FA permit Plan Review Requirements. He stated he would be down after lunch.
|
Miscellaneous action | | | 6/19/2003 | | DONE |
|
|
|
Request approved to begin installation without approved plans with Protex assuming full finacial responsibility for any potential changes necessary to comply with approved plans.
|
Plan resubmittals received | | | 6/18/2003 | | DONE |
|
|
|
|
Alarm Plan Check | | | 5/29/2003 | | FAIL |
|
|
|
Resubmittal required.
|
Application received | | | 5/28/2003 | | |
|
|
|
|