INSP-Final Inspection | 3/16/2004 | 3/16/2004 | 3/16/2004 | P | PASS |
Troy Cobbley
|
|
|
fire sprinkler underground finaled
|
DOC - Permit Finaled | 3/16/2004 | 3/16/2004 | 3/16/2004 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 3/16/2004 12:35:03 PM
|
INSP-Conference | 2/12/2004 | 2/13/2004 | 2/13/2004 | A | DONE |
Troy Cobbley
|
|
|
conference was for a door in the three hour wall between the new and the existing jail. Tom and I told Lee, who is the superintendant, that he could reuse the door frame as long as a certified company would relist the door frame 2/13/2004 10:12:53 AM
|
INSP-Conference | 1/21/2004 | 1/21/2004 | 1/21/2004 | A | FAIL |
Troy Cobbley
|
|
|
could not find the sprinkler contractor on site for the conference 1/21/2004 8:55:09 AM
|
INSP-Supply line flush | 7/31/2003 | 8/1/2003 | 8/1/2003 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 7/31/2003 at 3:56:18 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 1 2003 7:47AM.
|
INSP-Conference | 6/26/2003 | 6/26/2003 | 6/26/2003 | P | PASS |
Troy Cobbley
|
|
|
Underground hydrotest is OK 6/26/2003 2:16:35 PM
|
INSP-Conference | 6/18/2003 | 6/18/2003 | 6/18/2003 | P | PASS |
Troy Cobbley
|
|
|
Inspection was for supply line cover. The supply line is OK for cover 6/18/2003 3:48:31 PM
|
Inspection Record Card- Fire | 6/17/2003 | | 6/17/2003 | | DONE |
|
|
|
|
Telephone call | | | 6/17/2003 | | DONE |
|
|
|
CALLED JEFF PERMIT READY & FEE GIVEN
|
Issue permit | | | 6/17/2003 | | DONE |
|
|
|
|
Application received | | | 6/13/2003 | | |
|
|
|
Faxed in.
|
Plan assigned to (Bill) | 6/13/2003 | | 6/13/2003 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/13/2003 | | 6/13/2003 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/13/2003 | | DONE |
Bill Alexander
|
|
|
|