INSP-Final Inspection | 7/28/2003 | 7/29/2003 | 7/29/2003 | A | PASS |
Troy Cobbley
|
|
|
fire alarm finaled 7/29/2003 9:22:41 AM
|
DOC - Permit Finaled | 7/29/2003 | 7/29/2003 | 7/29/2003 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 7/29/2003 9:22:46 AM
|
INSP-Final Inspection | 7/28/2003 | 7/28/2003 | 7/28/2003 | P | NR |
Rick Jackson
|
|
|
Rick, This is other of the two projects that we spoke about this morning. They are right next to each other in the Blackeagle complex. Troy only had three comments for each building. 1.) Provide 18AH Batteries, 2.) Provide sinage on the riser room door, and 3.) provide definitions of the zones at the monitoring service. I will call you around noon to verify if you will have time this afternoon to final these out. Thanks, Jason Minnick c-###-####; Phone #: ###-#### Internet Inspection Request from: Jason Minnick; Phone #: ###-#### Internet Inspection Request from: Jason Minnick didn't test this system as this had the same problem as 9149 Blackeagle 7/28/2003 3:11:34 PM
|
INSP-Final Inspection | 7/24/2003 | 7/25/2003 | 7/25/2003 | A | FAIL |
Troy Cobbley
|
|
|
Provide 18ah batteries for the fire alarm panel, provide signage on the door. resend signals since all alarms came in as undefined at the central station 7/25/2003 10:03:33 AM
|
Plan assigned to (SAM) | 7/1/2003 | | 7/3/2003 | | DONE |
|
|
|
7/3/2003 11:16:57 M_F - activity updated through activity FIRA22 from case FIR03-00348.
|
Alarm Plan Check | | | 7/3/2003 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/3/2003 | | DONE |
|
|
|
|
Telephone call | | | 7/3/2003 | | DONE |
|
|
|
LEFT MESS THAT PERMIT IS READY & NO FEES
|
Issue permit | | | 7/3/2003 | | DONE |
|
|
|
|
Application received | | | 7/1/2003 | | |
|
|
|
|