Permit NumberFIR03-00375
StatusFinaled
Name DE BEST FIRE PROTECTION
Site Address 601 N PHILLIPPI ST
Project NameSPR STEIN DISTRIBUTING
Customer Number 
ePlanReview 
Description
(STEIN DISTRIBUTING CO., INC.) To install wet pipe fire sprinkler protection into the remodeled 1,768-ft/2 and expanded 1,768-ft/2 two-story office areas, located within an existing warehouse, for a total of 3536-ft/2. Work is related to include new walls around new the portion and upgrading walls and openings around existing office area to separate the office area from the warehouse with two-hour fire barrier walls. Includes a new vertical exit enclosure from second floor area, the removal and rebuilding of stairs on lower level, which access the warehouse area. This building is partially sprinklered for High Piled Storage use with a letter on file, to fully sprinkler the building by 2006. All fire sprinklers and related appurtenance within this permit work scope shall meet current NFPA 13-1999 standards, comply with the IFC-2000 and attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, in order to provide witness verification of compliance in meeting minimum code standards. This permit is attached to building permit: BLD03-00657.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/20/20044/20/20044/20/2004APASS
DetailsTroy Cobbley
Fire alarm finaled on 1/8/2004 under FIR03-00658
DOC - Permit Finaled4/20/20044/20/20044/20/2004APASS
DetailsTroy Cobbley
Finaled by inspector at 4/20/2004 9:23:16 AM
INSP-Final Inspection11/10/200311/10/200311/10/2003APART
DetailsTroy Cobbley
Temp occupancy given until the fire alarm system has been approved, installed and tested per Dave Millers permission
INSP-Sprinkler Rough-in/Hydro10/30/200310/31/200310/31/2003APASS
DetailsTroy Cobbley
wet system hydro test is ok 10/31/2003 1:49:46 PM
INSP-Sprinkler Rough-in/Hydro10/23/200310/24/200310/24/2003APART
DetailsTroy Cobbley
rough-in items from the first two inspections have been taken care of. Items at the riser still need to be completed. Hydro test failed. 10/24/2003 1:02:37 PM
INSP-Sprinkler Rough-in/Hydro10/6/200310/7/200310/7/2003PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/6/2003 at 1:41:13 PM. Contact: ###-####. okay to cover 2nd floor only except room 209 as it has protective cover on head; the branch line on the north side of the new addition is not installed; the new wet part of the riser is not complete; canopies not installed on all 401 heads; will need spare heads in head box; branch line on east side not complete; this building will now have over 20 heads and will require monitoring and does not have complete sprinkler coverage 10/7/2003 3:24:35 PM
INSP-Sprinkler Rough-in/Hydro10/1/200310/2/200310/2/2003APART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/1/2003 at 2:01:10 PM. area on first floor okay to cover except by the NE area by stair as SSU and SSP are too close together - reinspection needed to cover this area; sidewall installed under stair instead of pendant as shown on plans 10/2/2003 9:52:07 AM
Inspection Record Card- Fire8/1/2003 8/1/2003 DONE
Issue and Print Permit  8/1/2003 DONE
Sprinkler Plan Check7/25/2003 7/31/2003 PASS
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  7/31/2003 DONE
DetailsBill Alexander
Plan assigned to (Bill)7/9/2003 7/31/2003 DONE
7/31/2003 10:01:09 JWA - activity updated through activity FIRA22 from case FIR03-00375.
Plan resubmittals received  7/25/2003 DONE
Telephone call  7/22/2003 DONE
Review failed called for pick up
Sprinkler Plan Check7/9/2003 7/21/2003 FAIL
DetailsBill Alexander
A. Second floor cavity protection is not considered a "small room" and will not be allowed to be spaced as such. Must meet 5-6.2.2.

B. Light Hazard protection may be designed for up to 225-ft/2 spacing (with exceptions) and this design submitted (was verified for a maximum spacing of 186-ft/2 for densities of .10. Limits for small room rule allow spacing off one wall up to 9'-0", but maximum allowable area of protection cannot exceed the design proven which is: 186-ft/2. Office #205 even exceed maximum allowed if proven at 225-ft/2?

C. Trapeze hangers appear to be used for the roof main piping? Plans provide not location of roof truss supports. Include the location of truss support, span and provide the pipe size and type installing with the trapeze hangers. Where a pipe is suspended from a pipe trapeze of a diameter less than the diameter of the pipe being supported, ring, strap, or clevis hangers of the size corresponding to the suspended pipe shall be used on both ends. Include ring sizes on the trapeze. (6-1.1.3)

D. Provide data submittals on the "Riser Check" installing.

E. Show and/or provide a forward flow backflow test connection in accordance with 5-15.4.6.1 for provisions of meeting NFPA 13:10-2.6. Calculations provided (faxed) do not verify flows through piping out of this structure.
Miscellaneous action  7/21/2003 DONE
Took failed plans to the front "call" desk for calling and returning.
Application received  7/9/2003