INSP-Final Inspection | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PASS |
Rick Jackson
|
|
|
|
INSP-Final Inspection | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PASS |
Rick Jackson
|
|
|
|
DOC - Permit Finaled | 11/5/2003 | 11/5/2003 | 11/5/2003 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 11/5/2003 2:13:40 PM
|
INSP-Alarm Testing | 10/10/2003 | 10/14/2003 | 10/14/2003 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/10/2003 at 11:38:39 AM. Contact: ###-####. strobe not working in corridor 204b; device descriptors don't match acutual assigned room numbers (signs on wall next to rooms) and this was identified at the final inspection of the first phase to open the terminal 10/14/2003 2:15:52 PM
|
Inspection Record Card- Fire | 10/1/2003 | | 10/1/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/1/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/1/2003 | | DONE |
|
|
|
Spoke with Chris told permit ready & fees
|
Issue permit | | | 10/1/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 8/11/2003 | | 9/30/2003 | | DONE |
|
|
|
|
Alarm Plan Check | | | 9/30/2003 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2003 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/3/2003 | | DONE |
|
|
|
|
Miscellaneous action | | | 8/20/2003 | | |
|
|
|
Faxed request for the permit application to include the Building Occupancy Groups.
|
Alarm Plan Check | | | 8/20/2003 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Chris Willis 8/20/2003.
|
Application received | | | 8/11/2003 | | |
|
|
|
|