DOC - Permit Finaled | 11/28/2003 | 11/28/2003 | 11/28/2003 | A | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 11/28/2003 9:53:36 AM
|
INSP-Alarm Testing | 11/26/2003 | 11/26/2003 | 11/28/2003 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/26/2003 at 8:32:06 AM. Contact: ###-####. addresses 51 and 52 were used 11/28/2003 9:53:18 AM
|
Issue and Print Permit | | | 9/17/2003 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 8/12/2003 | | 9/10/2003 | | PASS |
|
|
|
9/10/2003 16:03:04 M_F - activity updated through activity FIRA22 from case FIR03-00457.
|
Miscellaneous action | | | 9/10/2003 | | |
|
|
|
Received e-mail confirmation from Paul Marcolina that there is no building permit associated with this fire alarm permit.
|
Alarm Plan Check | | | 9/10/2003 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2003 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/10/2003 | | 9/10/2003 | | DONE |
|
|
|
|
Telephone call | | | 9/10/2003 | | DONE |
|
|
|
left message for Pauol that permit is ready & fees
|
Permit Ready to Issue | | | 9/10/2003 | | DONE |
|
|
|
|
Miscellaneous action | | | 8/29/2003 | | |
|
|
|
Sent an e-mail to Paul Marcolina, the building permit BLD03-01902 is for BLDG 15, not BLDG 16 as the fire alarm permit application states. I requested clarification from Paul. These plans will be on hold until I receive clarificaiton.
|
Miscellaneous action | | | 8/22/2003 | | |
|
|
|
Waiting for building permit (BLD03-01902) to be approved. Fire alarm plans on hold.
|
Application received | | | 8/12/2003 | | |
|
|
|
|