INSP-Final Inspection | 10/31/2005 | 10/31/2005 | 10/31/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm permit finaled
|
FIR-Aging Inspection | 10/24/2005 | 10/24/2005 | 10/31/2005 | | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 7/28/2005 | 7/28/2005 | 8/1/2005 | | NR |
Troy Cobbley
|
|
|
Per Brian with AIC he will contact the owner again to provide the knox key box.
|
INSP-Conference | 5/26/2005 | 5/26/2005 | 5/26/2005 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Brian with AIC Solutions and let him know that all that is needed is the Knox Key box.
|
FIR-Aging Inspection | 4/6/2005 | 4/6/2005 | 4/6/2005 | P | PEND |
Forrest France
|
|
|
I called Brian with AIC solutions, ###-####, and left a message on his voice mail requesting status of the fire alarm installation
|
INSP-Final Inspection | 2/4/2005 | 2/4/2005 | 2/4/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide knox key box. The tamper switches for the backflow preventor did not annunciate separately from the other tamper switch as required by IFC 903.4.1. Need record of completion nfpa form at final. 2/4/2005 3:16:57 PM
|
Issue permit | | | 1/20/2005 | | |
|
|
|
|
Alarm Plan Check | | | 1/19/2005 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/19/2005 | | 1/19/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/19/2005 | | DONE |
|
|
|
Spoke with Brian and told him that permit is ready & fees///1/19/05 4:15pm BAS
|
Plan resubmittals received | | | 1/10/2005 | | DONE |
|
|
|
|
Meeting | | | 1/4/2005 | | DONE |
|
|
|
Met with Burle. Two items:
First, latching supervisory signals. Believe he has two options, one is new firmware from Notifier and the second would be to request permission from AHJ for the panel to remain.
Smoke roll up and held open doors are not required by code. Main roll up should be secured in the open position for egress route as defined by the BLD03 permit plans.
All doors may be disabled and smoke detectors removed. If the door hold open is left in place, the door will need to comply with NFPA 72.
|
INSP-Final Inspection | 12/16/2004 | 12/17/2004 | 12/17/2004 | P | FAIL |
Troy Cobbley
|
|
|
Battery calcs, flow switch, battery supervision and smoke detectors on the east side of building (5 total) operate correctly. Inspection stopped after finding the items listed. The monitoring company is not getting all of the signals sent such as Phone line 1 and low battery. Smoke detectors on the west half of the building annunciate locally but do not report to the panel. The tamper switches supervisory signal is latching and is not supposed to per nfpa 72 4.4.3.2.4. Per the manufacturer the panel can't be reprogrammed. 12/17/2004 1:56:55 PM
|
Issue and Print Permit | | | 12/16/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 12/14/2004 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/14/2004 | | 12/14/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/14/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 12/8/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/7/2004 | | DONE |
|
|
|
Spoke with Brian Richard (AIC), riser indicates 6 zones, new FACP is only capable of 5. Matrix does not include the smoke doors. Brian will get new information to me ASAP.
|
Plan resubmittals received | | | 12/1/2004 | | |
|
|
|
|
INSP-Final Inspection | 11/16/2004 | 11/17/2004 | 11/17/2004 | P | CANC |
Troy Cobbley
|
|
|
A new fire alarm panel has been installed. Contractor needs to resubmit plans for plan modifications 11/17/2004 3:45:38 PM
|
INSP-Final Inspection | 10/25/2004 | 10/25/2004 | 10/25/2004 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was stopped due to so many items being incorrect. Phone lines are not being supervised. Smoke detector installed is not the one submitted. Supervisory signal latches. No map of initiating devices. Need zone description at annunciator. No one to test the new tamper switches. Strobe does not work.
|
CHANGE STATUS TO (ISS) | | | 5/17/2004 | | DONE |
|
|
|
permit issued
|
Plan assigned to (SAM) | 9/29/2003 | | 5/13/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 5/13/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/13/2004 | | DONE |
|
|
|
|
Case Summary | | | 5/13/2004 | | |
|
|
|
|
Inspection Record Card- Fire | 5/13/2004 | | 5/13/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/13/2004 | | DONE |
|
|
|
|
Telephone call | | | 5/13/2004 | | DONE |
|
|
|
permit ready and fee due
|
Issue and Print Permit | | | 5/13/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 5/5/2004 | | |
|
|
|
|
INSP-Conference | 3/9/2004 | 3/9/2004 | 3/9/2004 | A | DONE |
Troy Cobbley
|
|
|
Odie with Steed Construction called wanting to know the status of the fire alarm drawings. I quoted the history.
|
Telephone call | | | 3/8/2004 | | DONE |
|
|
|
Called Brian Richard at AIC to inform him that there are fire rated roll up doors associated with the smoke detectors. He is going to douheck the spacing in the corridors to the east and send over information.
|
INSP-Conference | 3/3/2004 | 3/3/2004 | 3/3/2004 | A | DONE |
Troy Cobbley
|
|
|
At Mary's request I stopped at this project to verify if smoke detectors are installed and if possible the reason they are installed. I found smoke detectors installed on the left hand side of the lobby at three fire doors and what appears to be area coverage through out the office area to the right of the lobby. The smoke detectors at the fire doors are mounted on the walls on the lobby side and appear to exceed 12" down from the ceiling
|
Plan resubmittals received | | | 2/24/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/28/2003 | | DONE |
|
|
|
Left a message for Marty at AIC. Checking up on the clarification for the smoke detectors.
|
Telephone call | | | 10/28/2003 | | DONE |
|
|
|
Brian called back and I explained the partial area coverage on the first floor of the bldg. He said he would look into it.
|
Telephone call | | | 10/15/2003 | | DONE |
|
|
|
Requires clarification of occupancy to determine automatic detection requirements for existing devices on first floor. Spoke with Marty, he is going to go back to the architect for more information.
|
Plan resubmittals received | | | 10/8/2003 | | DONE |
|
|
|
Received information that was requested for the application and riser.
|
Miscellaneous action | | | 10/7/2003 | | DONE |
|
|
|
Faxed request for riser diagram and complete application information.
|
Application received | | | 9/29/2003 | | |
|
|
|
|