INSP-Final Inspection | 1/8/2004 | 1/8/2004 | 1/8/2004 | A | PASS |
Troy Cobbley
|
|
|
|
DOC - Permit Finaled | 1/8/2004 | 1/8/2004 | 1/8/2004 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 1/8/2004 10:01:37 AM
|
Miscellaneous action | | | 1/2/2004 | | DONE |
|
|
|
Recived and reviewed some piping (faxed 12/312/03) which were incorrect on the plans and needed modified.
|
INSP-Final Inspection | 12/30/2003 | 12/31/2003 | 12/31/2003 | A | FAIL |
Troy Cobbley
|
|
|
Inspection was for the sprinkler contractor completing the items on the correction notice. The sprinkler system still needs a final inspection 12/31/2003 12:29:52 PM
|
INSP-Supply line flush | 12/29/2003 | 12/30/2003 | 12/30/2003 | A | PART |
Troy Cobbley
|
|
|
Underground flush and forward flow test of the back flow preventer is OK 12/30/2003 9:53:19 AM
|
INSP-Sprinkler Rough-in/Hydro | 12/24/2003 | 12/29/2003 | 12/29/2003 | A | PART |
Troy Cobbley
|
|
|
Underground and Overhead hydro tests are OK. I did a rough-in inspection for the rest of the overhead sprinkler piping. Look at the city approved plans for locations that need attention. 12/29/2003 12:59:19 PM
|
INSP-Supply line flush | 12/24/2003 | 12/29/2003 | 12/29/2003 | P | CANC |
Troy Cobbley
|
|
|
Inspection was for a underground flush. The contractor could not get United Water there to open the valve 12/29/2003 4:44:27 PM
|
INSP-Sprinkler Rough-in/Hydro | 11/20/2003 | 11/21/2003 | 11/21/2003 | A | PART |
Troy Cobbley
|
|
|
hard lid areas ok to cover on the first floor 11/21/2003 11:05:49 AM
|
Issue and Print Permit | | | 10/31/2003 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 10/2/2003 | | 10/27/2003 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 10/23/2003 | | 10/27/2003 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2003 | | DONE |
|
|
|
|
Miscellaneous action | | | 10/27/2003 | | DONE |
|
|
|
Emailed notice and copy of review comments to Tom Easton.
|
Inspection Record Card- Fire | 10/27/2003 | | 10/27/2003 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/27/2003 | | DONE |
|
|
|
|
Telephone call | | | 10/27/2003 | | DONE |
|
|
|
Left message for Tom Easton that permit is ready & fees
|
Plan resubmittals received | | | 10/23/2003 | | DONE |
|
|
|
|
Miscellaneous action | | | 10/14/2003 | | DONE |
|
|
|
Emailed review notes. Plans taken to front desk for calling and returning.
|
Telephone call | | | 10/14/2003 | | DONE |
|
|
|
Called and left voice mail message for Tom Easton that plans failed and ready for pick up
|
Sprinkler Plan Check | 10/2/2003 | | 10/14/2003 | | FAIL |
Bill Alexander
|
|
|
Plan submittal design does not meet minimum code.
|
Application received | | | 10/2/2003 | | |
|
|
|
|