Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberFIR03-00613
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 322 E FRONT ST
Project Namealm - ID WATER CENTER-GARAGE
Customer Number 
ePlanReview 
Description
To provide for approved locations for manual pull stations, notification, fire/smoke damper control, sprinkler monitoring and fire pump monitoring in the basement of the building. The fire alarm panel is to be installed on an upper floor. The remainder of the building has not been submitted for permitting.

The associated building permit (BLD 02-00199) is to construct a new 127,5000 square foot, reinforced concrete underground parking garage (with 332 parking stalls) with grade level concrete structural support deck for future multi-story office, retail and residential buildings, as well as surface landscaping, parking and related site improvements. This permit is for the construction of the concrete structural shell only, no finishes including shafts, interior partitions, stairways, etc. are approved under this permit. A separate tenant improvement permit will be required to finish this garage for occupancy. This garage is fully fire sprinkled. All construction per the approved plans, attached comments, and attached ground water discharge agreement condition. This permit has been modified to allow construction in two phases. Phase one is the west 77,000 square foot portion between grid lines 1&13.5 and WA&WK. The second phase is the remaining 50,500 square foot east portion. See plan reviewer activity, dated 2/26/03 for more detailed information DRH01-00161/CUP01-00090/PC# 67-02/JCM IDAHO WATER CENTER (GARAGE SHELL)

THIS PERMIT IS FOR LOCATION OF DEVICES AND APPLICANCES ONLY IN THE BASEMENT. THE FACP IS TO BE INSTALLED IN AN UPPER FLOOR AND WILL REQUIRE ANOTHER SUBMITTAL (PERMIT) PRIOR TO ANY INSTALLATION.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/6/20048/6/20048/6/2004PPASS
DetailsRick Jackson
Final okay 8/6/2004 2:16:02 PM
DOC - Permit Finaled8/6/20048/6/20048/6/2004PPASS
DetailsRick Jackson
Finaled by inspector at 8/6/2004 2:16:08 PM
INSP-Final Inspection8/2/20048/2/20048/2/2004AFAIL
DetailsRick Jackson
Need updated map to reflect proper location of M1-013 8/2/2004 10:52:06 AM
INSP-Final Inspection8/2/20048/2/20048/2/2004AFAIL
DetailsRick Jackson
Need updated map to reflect proper location of M1-013 8/2/2004 10:52:06 AM
INSP-Final Inspection7/27/20047/28/20047/28/2004PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 7/27/2004 at 3:13:05 PM. Contact: ###-####. Inspection stopped due to sprinkler alarm problems - system not pre-tested; need updated plans to reflect added tampers/flows; descriptors needed for dry tampers/flows - all room numbers in basement are construction room numbers; need to verify inter-connection to PA2 7/28/2004 4:01:06 PM
Issue permit  6/21/2004 DONE
Telephone call  6/18/2004 DONE
I called Shawn to request a meeting to review and have him mark up the drawings in respects to the projected beam smoke detector locations per the manufacturer's cutsheets and to afford total coverage.
Meeting  6/18/2004 DONE
Shawn red-lined the drawings (plans) only to show proper locations for the projected smoke beam detectors. The projected smoke beam detector located in the rear elevator lobby of Elev #2, was replaced with a heat detector due to space requirements of the beam detector.
Alarm Plan Check  6/18/2004 PASS
Approved pending field inspection of fire alarm permit comments.
Miscellaneous action  6/18/2004  
A complete resubmittal of teh plan modifications to this permit is required prior to finalization of the fire alarm permit.
PLANS/APPL TAKEN TO FRONT DESK  6/18/2004 DONE
Inspection Record Card- Fire6/18/2004 6/18/2004 DONE
Permit Ready to Issue  6/18/2004 DONE
Telephone call  6/14/2004 DONE
I called Shawn Meador with Synergy and explained the building permit modifications on the plans were more extensive than originally thought. I stated that we could proceed in two ways, one would be he could red-line the drawings I have now, or two he could resubmit new plans. He'll mark up the existing.
Miscellaneous action  5/20/2004 DONE
HOLD plans. I spoke with John Menard. The architect needs to resubmit plans that show the modifications based upon the letter (from PDS) with the alternatives.
Telephone call  5/20/2004 DONE
I called Shawn (Synergy) to inform him that the architect needs to resubmit plans that show the modifications based upon the letter (from PDS) with the alternatives. The FA plans are on HOLD until the resubmittal is approved by PDS.
Plan resubmittals received  5/18/2004 DONE
Received fax from Shawn (Synergy), from PDS that approves the alternative to the FSDs.
Telephone call  5/13/2004 DONE
HOLD - FA Plans. I called Shawn at Synergy to advise him that the fire/smoke damper (FSD) that was associated with the Electrical Generator room 106, had been removed. I explained that I had discussed this with John Menard (BCPDS) and John stated that the architect would need to submit modifications to the building permit to delete the FSD. I asked Shawn to please notify the architect that they would need to submit plan modifications to the city and to please monitor the BLDG permit resubmittal and let me know when it passed. At that time, I would process the fire alarm plans and get the permit issued.
Plan resubmittals received  5/4/2004  
INSP-Conference4/1/20044/1/20043/30/2004APART
DetailsRick Jackson
Stop work order issued on fire alarm system in basement; given to Mike Wilson of Turner-McAlvain
Telephone call  3/30/2004 DONE
Courtesy phone call to Wes Smith to let him know that Rick Jackson was going to go over to the job site and post a "Stop Work Order" for the Fire Alarm system. The issue of the smoke detectors for the fire/smoke dampers is still the question. Wes stated he would make a phone call and see if anyone has come up with a solution.
Miscellaneous action  3/18/2004 DONE
HOLD. Spoke with Mike Simmons of ZGA. There is a proposal for a smoke detector that will function at 0 deg. They are waiting on an engineering evaluation.
Plan resubmittals received  3/4/2004  
Miscellaneous action  2/20/2004 HOLD
Plans are on hold. Applicant states the FSDs are being removed, there has been to resubmittal to the BLDG Dept for the change.
Telephone call  2/18/2004 DONE
Shawn (Synergy), resubmittals should be clouded, could he please come down and update the resubmittals, he stated he would.
Plan resubmittals received  2/10/2004  
Telephone call  10/30/2003 DONE
Spoke with John Parry of Sparling Engineers. (original design) 1-###-#### FSDs were called for in the basement by the mechanical engineer. The base design was handed over to a vendor for design build. I stated that I would write up the comments and get them back to the applicant.
Alarm Plan Check  10/30/2003 FAIL
Resubmittal required. Faxed comments to Chris Willis at Simplex and Wes Smith at Synergy 10/30/2003.
Telephone call  10/28/2003 DONE
Spoke with Wes Smith regarding multiple comments for the design. Told him the review would be completed tomorrow and I would send comments to Chris Willis at Simplex-Grinnell (applicant) and to Wes.
Telephone call  10/23/2003 DONE
Require clarification for review. Left a message for Chris Willis, Simplex-Grinnell.
Application received  10/9/2003  
Plan assigned to (SAM)10/9/2003