Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberFIR03-00659
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 11193 W EMERALD ST
Project NameSPR Fresca Mexican Foods Ph-2
Customer Number 
ePlanReview 
Description
(FRESCA MEXICAN FOODS - PHASE 2) To extend a new wet pipe fire sprinkler system off an existing header (installed under FIR02-00385), into areas identified on the plans as Phase 2. This consists of Food Process Packaging, High Piled Combustible Storage, standard Offices and related support areas. Fire sprinklers used for area increase. The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is not attached to any building permit, but is part of a fire protection upgrade agreement on file with the Boise Fire Dept, negotiated with Dave Miller.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/15/20043/16/20043/16/2004APASS
DetailsTroy Cobbley
fire sprinklers finaled 3/16/2004 3:12:46 PM
DOC - Permit Finaled3/16/20043/16/20043/16/2004PPASS
DetailsTroy Cobbley
Finaled by inspector at 3/16/2004 3:13:16 PM
INSP-Sprinkler Rough-in/Hydro3/12/20043/15/20043/15/2004AFAIL
DetailsTroy Cobbley
Earth quaking is not quite finished at north drop down at second floor offices 3/15/2004 3:28:47 PM
INSP-Sprinkler Rough-in/Hydro3/11/20043/12/20043/12/2004PFAIL
DetailsTroy Cobbley
Hydro test failed. Cracked pipe. 3/12/2004 2:51:01 PM
INSP-Final Inspection3/11/20043/12/20043/12/2004PFAIL
DetailsTroy Cobbley
Provide spare sprinkler heads in head cabinet. Provide signage. Verify pressure relief vavle. Hydro test system. Tag new sprinkler system. Verify inspection tag for the existing fire sprinkler system and fire pump is current. Finish earth quake bracing. 3/12/2004 2:53:46 PM
Inspection Record Card- Fire2/6/2004 2/6/2004 DONE
Issue and Print Permit  2/6/2004 DONE
Sprinkler Plan Check2/4/2004 2/5/2004 PASS
Plan assigned to (Bill)2/4/2004 2/5/2004 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/5/2004 DONE
Permit Ready to Issue  2/5/2004 DONE
Telephone call  2/5/2004 DONE
spoke with Greg --- permit is ready.
Issue and Print Permit  2/3/2004 DONE
Inspection Record Card- Fire11/3/2003 11/3/2003 DONE
Permit Ready to Issue  11/3/2003 DONE
Telephone call  11/3/2003 DONE
permit ready and fee due
Plan assigned to (Bill)10/30/2003 10/31/2003 DONE
Sprinkler Plan Check10/30/2003 10/31/2003 PART
DetailsBill Alexander
PLANS/APPL TAKEN TO FRONT DESK  10/31/2003 DONE
Miscellaneous action  10/31/2003 DONE
Copy if review notes emailed to Greg Johnson.
Application received  10/30/2003