INSP-Sprinkler Rough-in | 4/12/2004 | 4/13/2004 | 4/13/2004 | A | PASS |
Troy Cobbley
|
|
|
fire sprinklers finaled 4/13/2004 8:23:25 AM
|
DOC - Permit Finaled | 4/13/2004 | 4/13/2004 | 4/13/2004 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 4/13/2004 8:23:46 AM
|
INSP-Final Inspection | 4/12/2004 | 4/12/2004 | 4/12/2004 | P | FAIL |
Troy Cobbley
|
|
|
forward flush failed through the 2" drain. Provide heat for the riser room 4/12/2004 2:32:20 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2004 | 4/6/2004 | 4/6/2004 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed 10/15/2003 11:24:50 PM
|
INSP-Sprinkler Rough-in/Hydro | 4/5/2004 | 4/5/2004 | 4/5/2004 | P | PASS |
Troy Cobbley
|
|
|
dry system hydro test passed. 24 hour air test started at 2:45 with 50psi 4/6/2004 8:17:47 AM
|
INSP-Supply line flush | 3/31/2004 | 3/31/2004 | 3/31/2004 | P | PASS |
Troy Cobbley
|
|
|
above ground wet system and underground hydro test ok. Flush of the underground supply line flush is ok 3/31/2004 4:13:12 PM 3/31/2004 4:13:36 PM
|
Issue and Print Permit | | | 3/31/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/4/2004 | | |
|
|
|
|
Telephone call | | | 3/4/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Inspection Record Card- Fire | 3/4/2004 | | 3/4/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/3/2004 | | 3/3/2004 | | PASS |
Bill Alexander
|
|
|
Possible resubmittal required due to forward flow piping on the riser?
|
Plan assigned to (Bill) | 2/27/2004 | | 3/3/2004 | | |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/27/2004 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 2/11/2004 | 2/11/2004 | 2/11/2004 | P | FAIL |
Troy Cobbley
|
|
|
provide hangers on the 1 1/4" supplies and the sprinkler pendant in the mechanical room is still overspaced 2/11/2004 3:40:51 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/6/2004 | 2/9/2004 | 2/9/2004 | P | FAIL |
Troy Cobbley
|
|
|
Inspection was for the rough-in and cover of the first floor. 1 1/4" tie in's are not done, pendant head overspace in mechanical room, pendant head overspaced understairs in connecting corridor and piping not complete in rooms as marked on approved plans. Outside canopies are ok to cover 2/9/2004 4:21:17 PM
|
INSP-Sprinkler Rough-in/Hydro | 2/5/2004 | 2/6/2004 | 2/6/2004 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 2/5/2004 at 3:19:45 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Feb 6 2004 9:22AM.
|
INSP-Sprinkler Rough-in/Hydro | 1/29/2004 | 1/29/2004 | 1/29/2004 | A | PART |
Troy Cobbley
|
|
|
sprinkler piping on the second floor between the two large beams is ok to cover. The north and south canopies are ok to cover except for the end of each branchlines. These need re-inspected due to blocked upright sprinkler coverage
|
INSP-Sprinkler Rough-in/Hydro | 1/27/2004 | 1/28/2004 | 1/28/2004 | A | CANC |
Troy Cobbley
|
|
|
areas needing inspection are not ready 1/27/2004 3:17:22 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2004 | 1/23/2004 | 1/23/2004 | A | FAIL |
Troy Cobbley
|
|
|
hangers must go to top chord. Provide head in mech. room. Provide insulation in the void in the east canopy. tent plastic piping. Inspection was for the central part of the second floor (area between the beams). 1/23/2004 2:04:26 PM
|
Issue and Print Permit | | | 1/5/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 12/17/2003 | | 12/30/2003 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/17/2003 | | 12/30/2003 | | PART |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2003 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/30/2003 | | 12/30/2003 | | DONE |
|
|
|
|
Telephone call | | | 12/30/2003 | | DONE |
|
|
|
called permit ready & fee given 12-30-03 12:25 ///dld
|
Application received | | | 12/17/2003 | | |
|
|
|
|
Sprinkler Plan Check | 2/27/2004 | | | | |
Bill Alexander
|
|
|
|