INSP-Final Inspection | 6/28/2004 | 6/29/2004 | 6/29/2004 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm finaled 6/29/2004 9:59:06 AM
|
DOC - Permit Finaled | 6/29/2004 | 6/29/2004 | 6/29/2004 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 6/29/2004 9:59:10 AM
|
INSP-Final Inspection | 6/15/2004 | 6/18/2004 | 6/18/2004 | A | FAIL |
Troy Cobbley
|
|
|
Provide a/v coverage in the corridor per the last correction notice. Change the 30cd strobe to 15cd in Rob's office. Provide signage on doors to facp and sprinkler riser per review note #23. Test low air signal on dry pipe riser 6/18/2004 9:33:41 AM
|
INSP-Final Inspection | 6/9/2004 | 6/14/2004 | 6/14/2004 | A | CANC |
Troy Cobbley
|
|
|
Inspection was cancelled by Rob with Protex 6/14/2004 8:33:34 AM
|
Issue and Print Permit | | | 5/28/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 5/25/2004 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/25/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/25/2004 | | DONE |
|
|
|
|
Telephone call | | | 5/25/2004 | | DONE |
|
|
|
permit ready and fee due
|
Plan resubmittals received | | | 5/20/2004 | | |
|
|
|
|
Issue and Print Permit | | | 5/5/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 4/30/2004 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/30/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/30/2004 | | DONE |
|
|
|
left a message for Rob -- permit is ready.
|
Plan resubmittals received | | | 4/15/2004 | | |
|
|
|
|
INSP-Final Inspection | 3/12/2004 | 3/18/2004 | 3/18/2004 | A | FAIL |
Troy Cobbley
|
|
|
Resubmit fire alarm plans that include all devices including the second dry pipe valve, backflow preventor and the additional three duct smoke detectors. End of line voltage on the notification circuits exceeds 21.6 volts(nfpa 72, 7.3.2.3). Provide verification/explanation on resubmittals on why remaining hvac units do not have automatic shutdown per IMC. Office and corridor areas that open into the new addition must be brought up to code compliance. Only the items listed above have been inspected and addressed. All other items to be verified when resubmitted plans have been issued 3/18/2004 9:41:04 AM
|
Miscellaneous action | | | 2/13/2004 | | DONE |
|
|
|
Requirement of comment #18 (duct detectors shall be provided as requried by the Code under which the units were installed.
Areas -front entry customer waiting and Nursing admin area are fed by multiple units that summed are over 2000 cfm. Per the 1991 UMC, single systems over 2000 cfm are to be monitored for shutdown.
Therefore the monitoring air handlers for these two areas will not be required.
|
INSP-Final Inspection | 2/12/2004 | 2/12/2004 | 2/12/2004 | A | PART |
Troy Cobbley
|
|
|
Temporary occupancy was given until all of the fire mains are upgraded per plans submitted to boise city and the fire alarm system is completed
|
Plan assigned to (Mary) | 1/12/2004 | | 2/9/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 2/9/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/9/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/9/2004 | | DONE |
|
|
|
|
Telephone call | | | 2/9/2004 | | DONE |
|
|
|
called permit ready 2-9-04 37 ///dld
|
Issue and Print Permit | | | 2/9/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/9/2004 | | 2/9/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/3/2004 | | DONE |
|
|
|
|
Telephone call | | | 1/26/2004 | | DONE |
|
|
|
Talked to Rob at Protex, inquired why the FA system had not been expanded into the new addition. He stated that the designer was CSHQA. I said I would call them.
|
Telephone call | | | 1/26/2004 | | DONE |
|
|
|
Called Stephanie Cribbs at CSHQA. She stated that they wrote the specifications, but the electrical contractor was responsible for the design. The FA submittals were to be submitted to them for review prior to a city submittal. I told her that I would write a quick comment (denial) regarding the condition of the submittal and fax to ROb at Protex and a copy to her at CSHQA.
|
Alarm Plan Check | | | 1/26/2004 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Rob at Protex and Stephanie at CSHQA.
|
Application received | | | 1/12/2004 | | |
|
|
|
|