INSP-Final Inspection | 5/21/2004 | 5/24/2004 | 5/24/2004 | A | PASS |
Rick Jackson
|
|
|
Phone #: ###-#### Internet Inspection Request from: Wayne Berry
|
DOC - Permit Finaled | 5/24/2004 | 5/24/2004 | 5/24/2004 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 5/24/2004 1:34:01 PM
|
INSP-Final Inspection | 5/12/2004 | 5/12/2004 | 5/12/2004 | P | FAIL |
Rick Jackson
|
|
|
Two sprinkler heads were not replaced to make clearance for RF units on second floor 5/12/2004 3:24:45 PM
|
INSP-Final Inspection | 5/6/2004 | 5/6/2004 | 5/6/2004 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 5/6/2004 at 6:50:16 AM. Contact: ###-####. Alarms not ready so this will be inspected with the alarm final 5/6/2004 8:48:11 AM
|
INSP-Sprinkler Rough-in/Hydro | 4/28/2004 | 4/29/2004 | 4/29/2004 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 4/28/2004 at 1:06:32 PM. Contact: ###-####. Hydro was okay; heads added under duct are too close to other heads and will need to be relocated 4/29/2004 2:04:53 PM
|
INSP-Final Inspection | 4/28/2004 | 4/29/2004 | 4/29/2004 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 4/28/2004 at 1:07:17 PM. Contact: ###-####. Hydro okay; heads added under duct are too close to other heads and will need to be relocated 4/29/2004 2:05:21 PM
|
Issue and Print Permit | | | 3/26/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 2/17/2004 | | 3/25/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 3/22/2004 | | 3/25/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/25/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/25/2004 | | 3/25/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/25/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Permit Ready to Issue | | | 3/25/2004 | | DONE |
|
|
|
|
Telephone call | | | 3/25/2004 | | DONE |
|
|
|
e-mailed paul & darla that permit is ready
|
Miscellaneous action | | | 3/23/2004 | | DONE |
|
|
|
Emailed a notice to Nick Anderson/Designer that a "Fire Sprinkler Cover Sheet" and claculations for the main floor must be submitted with this resubmital package received 3/22/04.
|
Plan resubmittals received | | | 3/22/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 2/18/2004 | | 2/26/2004 | | FAIL |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 2/26/2004 | | DONE |
|
|
|
Faxed copy of failed review to: ###-####, and took plans to the front desk for returning.
|
Application received | | | 2/17/2004 | | |
|
|
|
|