INSP-Final Inspection | 6/26/2006 | 6/28/2006 | 6/28/2006 | A | PASS |
Forrest France
|
|
|
Required corrections have been completed, fire alarm work is satisfactory, permit finaled.
|
Agreement of Future work | 10/25/2004 | 12/31/2008 | 6/26/2006 | | DONE |
|
|
|
New Upgrade Agreement put in place. Supersedes older agreements. Work still in progress.
|
INSP-Alarm Testing | 2/28/2006 | 3/3/2006 | 3/3/2006 | A | PART |
Forrest France
|
|
|
Provide resubmittals for changes in the basement (Angels), provide updated building map, add notification in the break room on 8th floor.
|
INSP-Alarm Testing | 2/13/2006 | 2/16/2006 | 2/16/2006 | A | CANC |
Forrest France
|
|
|
would like it at 8AM if possible let me know. Internet Inspection Request from: Rick Groom Inspection cancelled from web by: Rick Groom
|
INSP-Alarm Testing | 2/6/2006 | 2/9/2006 | 2/8/2006 | A | CANC |
Troy Cobbley
|
|
|
WOULD LIKE TO DO THIS AT 8AM IF POSSIBLE, IF NOT LET ME KNOW... Internet Inspection Request from: Rick Groom Inspection cancelled from web by: Rick Groom
|
INSP-Alarm Testing | 1/24/2006 | 1/25/2006 | 1/25/2006 | A | PART |
Forrest France
|
|
|
Tested functionality of the notification and voice evac systems only, approved plans for the 8th floor not available for review.
|
Case Summary | | | 1/23/2006 | | |
|
|
|
|
INSP-Alarm Testing | 1/11/2006 | 1/18/2006 | 1/11/2006 | A | CANC |
Forrest France
|
|
|
COULD TAKE ALL DAY, MAYBE 2 DAYS... Internet Inspection Request from: Rick Groom Inspection cancelled from web by: Rick Groom
|
Case Summary | | | 1/10/2006 | | DONE |
|
|
|
|
Telephone call | | | 9/19/2005 | | DONE |
|
|
|
Left a message for Dave Maxwell that we needed to get this permit completed and to please call me back.
|
Issue and Print Permit | | | 4/8/2005 | | DONE |
|
|
|
|
Telephone call | | | 4/6/2005 | | DONE |
|
|
|
tlk to rick groom that permit and fees are ready to be picked up
|
Inspection Record Card- Fire | 4/5/2005 | | 4/5/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/5/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 4/4/2005 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2005 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/31/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/2/2005 | | DONE |
|
|
|
|
INSP-Final Inspection | 1/27/2005 | 1/27/2005 | 1/27/2005 | A | PART |
Rick Jackson
|
|
|
All items have been corrected from previous inspection 1/27/2005 8:30:39 AM
|
Alarm Plan Check | | | 1/27/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/27/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/27/2005 | | 1/27/2005 | | DONE |
|
|
|
|
Telephone call | | | 1/27/2005 | | DONE |
|
|
|
Spoke with Rick and told him that permit is ready & fees///1/27/05 3:30pm BAS
|
Plan resubmittals received | | | 1/26/2005 | | DONE |
|
|
|
Received requested documents.
|
Telephone call | | | 1/24/2005 | | DONE |
|
|
|
Called Dave Maxwell...a condition for the 3rd floor included adding smoke detectors for door hold-opens and the drawings would be resubmitted with the upgrade. At this time, the 3rd floor has not been included. The firemans jacks have not been added to the 3rd floor. Dave will bring the appropirate drawings to insert into the drawing set to "complete" the submittal.
|
Plan resubmittals received | | | 1/19/2005 | | DONE |
|
|
|
|
INSP-Alarm Testing | 10/14/2004 | 10/15/2004 | 10/15/2004 | A | FAIL |
Rick Jackson
|
|
|
Rick we need to schedule this for 7am let me know if this will work for you... Internet Inspection Request from: Rick Groom Need updated maps; relocate detector on first floor away from diffuser; batteries per plans; need penthouse plans; smoke above panel 10/15/2004 9:37:30 AM
|
Issue and Print Permit | | | 9/8/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/3/2004 | | 9/3/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/3/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/3/2004 | | DONE |
|
|
|
talked with Dave Maxwell on phone regarding fees and permit ready to be picked up
|
Alarm Plan Check | | | 9/2/2004 | | PART |
|
|
|
This partial is for the Fire Alarm system components for the elevator controls only. The FA components will be tied into the existing FACP to expedite the elevator control upgrade.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/30/2004 | | |
|
|
|
|
Alarm Plan Check | | | 3/19/2004 | | HOLD |
|
|
|
Resubmittal required. No comments The plans submitted do not meet the upgrade agreement of FACP, 3 floors year 2003, and 3 floors every year thereafter. This submittal was for the entire core area, all floors.
|
Application received | | | 3/11/2004 | | |
|
|
|
|
Plan assigned to (Mary) | 3/11/2004 | | 3/11/2004 | | DONE |
|
|
|
|