INSP-Sprinkler Rough-in/Hydro | 5/6/2004 | 5/6/2004 | 5/6/2004 | P | PASS |
Rick Jackson
|
|
|
Erinie; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Minor changes were made due to wall changes - spacing maintained 5/6/2004 2:08:55 PM
|
DOC - Permit Finaled | 5/6/2004 | 5/6/2004 | 5/6/2004 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 5/6/2004 2:11:33 PM
|
Issue and Print Permit | | | 4/22/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 4/16/2004 | | 4/21/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/21/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 4/20/2004 | | 4/21/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/21/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/21/2004 | | 4/21/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/21/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/21/2004 | | DONE |
|
|
|
permit ready and fee due
|
Sprinkler Plan Check | 4/16/2004 | | 4/19/2004 | | FAIL |
Bill Alexander
|
|
|
Lack required data to start or provide a correct design review.
|
Telephone call | | | 4/19/2004 | | DONE |
|
|
|
12:15 - Called Nick Anderson - questions in regards to associated building permit. How much of plan FP2.1 is new (assume all shown on FP2.2 is new/added and/or relocated, etc., etc. No answer. Called paul Marcolina to pose the same questions, he said I would have to talk to the designer (Nick Anderson).
2:15 - Nick called and questioned him on scope of work. Found out that I am missing calculations for the basement ceiling plans, and design cover sheet for the underfloor system.
2:25 - Emailed Paul Marcolina and Nick Anderson that plans failed and require basics prior to starting a review.
|
Application received | | | 4/16/2004 | | |
|
|
|
|