INSP-Alarm Testing | 9/24/2004 | 9/27/2004 | 9/27/2004 | A | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 9/24/2004 at 1:10:42 PM. Contact: ###-####.
|
INSP-Final Inspection | 9/24/2004 | 9/24/2004 | 9/24/2004 | P | PASS |
Troy Cobbley
|
|
|
Fire alarm system finaled
|
DOC - Permit Finaled | 9/24/2004 | 9/24/2004 | 9/24/2004 | P | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 9/24/2004 2:11:19 PM
|
INSP-Final Inspection | 9/23/2004 | 9/23/2004 | 9/23/2004 | P | FAIL |
Troy Cobbley
|
|
|
Signals that the monitoring company are different that have been sent out, provide map at facp and drill holes for the duct detector housings 9/23/2004 12:15:56 PM
|
INSP-Final Inspection | 9/20/2004 | 9/20/2004 | 9/20/2004 | P | FAIL |
Troy Cobbley
|
|
|
Provide a/v's in rooms 115 and in the facp room as per plan. A/v's overspaced in 116, 103, 106, 107 and outside of toilet 124. Provide correct sample tube lenghts for the duct smoke detectors. Provide map for facp and stickers on the annunciators telling where the map is at. Test remaining duct smoke detectors in the sanctuary and daycare. Test a/v's on second floor. Provide lock outs on breakers. 9/20/2004 3:11:00 PM
|
INSP-Final Inspection | 9/17/2004 | 9/17/2004 | 9/17/2004 | P | FAIL |
Troy Cobbley
|
|
|
There are phone line problems. Contractor wants to reschedule for monday 9/17/2004 2:22:34 PM
|
Telephone call | | | 9/17/2004 | | DONE |
|
|
|
I phoned Bill Carter, Musgrove Engineering, to confirm the duct smoke detector configuration on the mechanical system in the Nursery/Preschool Building. THere are 9 AC units all have a duct smoke detector, AC-2 has two because of the ducting. By code, ERU 1 & 2 do not require HVAC shutdown, so the duct smoke detectors on those units have been removed.
|
Alarm Plan Check | | | 9/17/2004 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/17/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/17/2004 | | 9/17/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2004 | | DONE |
|
|
|
Left message for Matt that permit is ready & fees///9/17/04 8:50am BAS
|
Issue and Print Permit | | | 9/17/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/16/2004 | | DONE |
|
|
|
Called Matt Casey for clarification on the scope of work as the application stated "Resumbit plans & riser modification change".
See Additiional scope of work dated 9/16/2004 on the FIR04-00238 write up.
A revised matrix is required for the HVAC shutdown procedure in the Nursery/Preschool Building, he will fax. The battery calculations include the duct smoke detectors that are 120VAC, I requested a revised battery calculation, he will have Farren Eng. fax.
|
Plan resubmittals received | | | 9/16/2004 | | DONE |
|
|
|
Received faxed revised battery calculation from Farren Engineering.
|
Plan resubmittals received | | | 9/16/2004 | | DONE |
|
|
|
Received revised matrix for the mechanical units in the Nursery/Preschool building via fax from Matt Casey, Futuretech.
|
INSP-Alarm Testing | 9/13/2004 | 9/13/2004 | 9/13/2004 | P | CANC |
Troy Cobbley
|
|
|
Resubmitted fire alarm plans not approved yet 9/13/2004 11:26:49 AM
|
Plan resubmittals received | | | 9/13/2004 | | DONE |
|
|
|
|
INSP-Conference | 8/25/2004 | 8/25/2004 | 8/25/2004 | A | DONE |
Troy Cobbley
|
|
|
I was called out to this project for a fire sprinkler inspection and found wire installed overhead and into the conduit and back boxes. The fire alarm plans have not been issued for this project. This work was done by Future Tech, the fire alarm contractor. I notified Mary Froemke so that any possible double fees could be assessed.
|
INSP-Conference | 8/25/2004 | 8/25/2004 | 8/25/2004 | A | PASS |
Troy Cobbley
|
|
|
I spoke to Brian with Future Tech about placement of the duct smoke dectors. Since the hvac design has interconnections between the returns on all of the units, which is something I haven't seen before. I asked him to submitt to the fire alarm plan reviewer a design for the duct smoke detectors that meet IMC from a mechanical engineer for review and approval. Per the fire alarm contractor the mechanical engineer only showed duct detectors on two hvac units.
|
Issue and Print Permit | | | 8/25/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 8/24/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/24/2004 | | 8/24/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/24/2004 | | DONE |
|
|
|
|
Telephone call | | | 8/24/2004 | | DONE |
|
|
|
Spoke with Matt and told him that permit is ready & fees///8/24/04 9:25am BAM
|
Plan assigned to (Mary) | 4/19/2004 | | 8/24/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/18/2004 | | |
|
|
|
|
Alarm Plan Check | | | 8/12/2004 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Matt Casey 8/12/2004.
|
INSP-Conference | 8/9/2004 | 8/9/2004 | 8/9/2004 | P | DONE |
Troy Cobbley
|
|
|
I issued a citation to Romar Electric/Kurtis Carlson for violation of IFC 902.1 as adopted by Boise City Municipal Code section 7-01-02 for beginning installation of the fire alarm system without approved plans.
|
INSP-Conference | 8/6/2004 | 8/6/2004 | 8/6/2004 | P | DONE |
Troy Cobbley
|
|
|
I stopped at the project per Mary's request to verify if fire alarm work had been started without approved drawings. I found backboxes and conduit installed but no wiring. Per Andy Lieurance, the electrician that installed the boxes, who is with Romar, the boxes where installed during rough-in and he was then told to quit installing since it was FutureTechs job to install. I will talk to Dave Miller on Monday to verify that a citation will be issued. According to city records Romar has received two precitation letter already.
|
INSP-Conference | 8/6/2004 | 8/6/2004 | 8/6/2004 | P | DONE |
Troy Cobbley
|
|
|
I issued a stop work order for the fire alarm installation. Notice is posted on the southeast facing door
|
Alarm Plan Check | | | 8/5/2004 | | FAIL |
|
|
|
Resubmittal Required. Faxed comments to Matt Casey 8/5/2004.
|
Plan resubmittals received | | | 7/29/2004 | | |
|
|
|
|
Miscellaneous action | | | 6/18/2004 | | DONE |
|
|
|
Request from Matt Casey to "HOLD" plans. Scope of work has changed.
|
Plan resubmittals received | | | 6/18/2004 | | |
|
|
|
|
Alarm Plan Check | | | 5/18/2004 | | FAIL |
|
|
|
Resubmittal required. Faxed comments to Matt Casey Futuretech.
|
Telephone call | | | 5/17/2004 | | DONE |
|
|
|
Received building permit # from Matt Casey (Futuretech) BLD03-02403
|
Telephone call | | | 5/13/2004 | | DONE |
|
|
|
Left a message for Matt, haven't received a building permit # for this permit yet.
|
Miscellaneous action | | | 5/13/2004 | | DONE |
|
|
|
HOLD pending receiving building permit # from Matt Casey at Futuretech.
|
Telephone call | | | 5/4/2004 | | |
|
|
|
Follow up telephone call to Matt Casey to inquire about the building permit #. He has not received it yet, will get mack to me when he does.
|
Telephone call | | | 4/28/2004 | | DONE |
|
|
|
Application defines "new system in new building"; there was no BLDG permit number on the application. Matt Casey stated he would get it and call me back.
|
Application received | | | 4/19/2004 | | |
|
|
|
|