Case Summary | | | 2/3/2006 | | |
|
|
|
|
INSP-Final Inspection | 9/14/2005 | 9/14/2005 | 9/14/2005 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit finaled.
|
INSP-Final Inspection | 7/15/2005 | 7/15/2005 | 7/15/2005 | P | PART |
Forrest France
|
|
|
Provide seismic clearance at UG supply where it passes through the foundation wall, provide sinage at riser room door indicating its location.
|
INSP-Final Inspection | 6/21/2005 | 6/22/2005 | 6/22/2005 | A | PART |
Forrest France
|
|
|
Final pending inspection of heads in one room at the basement level to which access was denied, also need to provide seismic clearance at the underground supply where it passes through the foundation wall.
|
INSP-Sprinkler Rough-in/Hydro | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of basement, first floor, and antifreeze systems passed two hour test.
|
Issue permit | | | 5/24/2005 | | |
|
|
|
|
Sprinkler Plan Check | 5/10/2005 | | 5/20/2005 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/20/2005 | | DONE |
|
|
|
|
Telephone call | | | 5/20/2005 | | DONE |
|
|
|
tlk to jeff packham ###-#### that permit and fees are ready to be picked up
|
Plan resubmittals received | | | 5/10/2005 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | PART |
Troy Cobbley
|
|
|
See plans with todays date for areas ok to cover. Resubmittals are required for changes in piping, lobby and room above ceiling
|
INSP-Sprinkler Rough-in | 3/23/2005 | 3/23/2005 | 3/23/2005 | P | PASS |
Troy Cobbley
|
|
|
Spoke to Mike on phone. Area in question on first floor is ok to cover 3/23/2005 4:00:54 PM
|
INSP-Sprinkler Rough-in | 2/25/2005 | 2/25/2005 | 2/25/2005 | P | PART |
Troy Cobbley
|
|
|
See approved plans for locations in basement where the sprinkler piping is ok to cover. 2/25/2005 3:28:01 PM
|
INSP-Sprinkler Rough-in | 2/14/2005 | 2/14/2005 | 2/14/2005 | P | PART |
Troy Cobbley
|
|
|
See approved plans for first floor locations ok to cover 2/14/2005 4:07:28 PM
|
INSP-Sprinkler Rough-in | 2/1/2005 | 2/2/2005 | 2/2/2005 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Moore 2nd and 3rd floors hydro and r/i's all complete 2/2/2005 1:51:23 PM
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2005 | 1/31/2005 | 1/31/2005 | P | PART |
Rick Jackson
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice 2nd floor r/i and hydro okay 1/31/2005 3:11:11 PM
|
Inspection Record Card- Fire | 11/30/2004 | | 11/30/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/30/2004 | | DONE |
|
|
|
Spoke with Jeff and told him that permit is ready & fees///11/30/04 11:10am BAS
|
Issue and Print Permit | | | 11/30/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 11/30/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 11/17/2004 | | 11/29/2004 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 11/17/2004 | | 11/29/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/17/2004 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/19/2004 | 10/19/2004 | 10/19/2004 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Hydro okay on third floor and main feed from riser to third floor; still need resubmittals and will need to verify piping after approved 10/19/2004 3:39:55 PM
|
INSP-Sprinkler Rough-in | 10/15/2004 | 10/15/2004 | 10/15/2004 | P | FAIL |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Verified piping on third floor hallway only - need resubmittals due to changes and using flexheads 10/15/2004 1:54:01 PM
|
INSP-Conference | 8/26/2004 | 8/26/2004 | 8/26/2004 | P | PART |
Rick Jackson
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Met with Mike about the riser for floors - plans show in electrical closet but will not meet clearances from electrical panels per NEC; stair risers may work but will have to maintain IBC clearances at landings; plan modifications will be needed to reflect changes 8/26/2004 1:03:51 PM
|
Sprinkler Plan Check | 7/8/2004 | | 7/12/2004 | | PASS |
Bill Alexander
|
|
|
|
Plan assigned to (Bill) | 7/8/2004 | | 7/12/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/12/2004 | | 7/12/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/12/2004 | | DONE |
|
|
|
permit ready and fee due
|
CHANGE STATUS TO (ISS) | | | 7/12/2004 | | DONE |
|
|
|
picked up
|
Plan resubmittals received | | | 7/8/2004 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/28/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 6/15/2004 | | 6/25/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/24/2004 | | 6/25/2004 | | PART |
Bill Alexander
|
|
|
General:
1. Provide corrected and clarification of anti-freeze system, which shall include:
a. Drive thru canopy shall be protected with a minimum design of OH-1.
b. Piping plan shall correlate with calculations.
c. Provide location of loop systems tap (which shall correlate with plans).
d. Include supply piping on the basement floor plan and give the location of the same.
e. Add more nodes on the plans for verification and clarification of calcs.
f. Include manufacturer's data submittal of expansion chamber installing.
g. Include the elevation of the backflow device, etc.
Basement:
2. Provide piping section and configuration on main drain, gang drain and forward flow test connection and how and where they will be pipe out of this building. Include auxiliary drain information in the basement.
Plan FP-2, and FP-3
3. 1st floor tree piping in a lobby is not matching any piping design proven in any part of this structure. Provide clarification of what the designer has made to determine this is will meet minimum protection?
4. Clarify what is located in the center of the basement and 1st floor, which are not identified or protected?
5. Provide readable identification of all rooms, areas and ceiling elevations.
6. Clarify the occupancy hazard/use of the concrete decks.
7. Identify all areas with Obstructed Construction on the plans. (This is brought out due to the detail at "TJI" overbuild).
Plan FP-4 and FP-5
8. 1st floor tree piping in a lobby is not matching any piping design proven in any part of this structure. Provide clarification of what the designer has made to determine this is will meet minimum protection?
9. Provide readable identification of all rooms, areas and ceiling elevations.
10. Fire sprinkler head in top of elevator shaft in the southwest corner is overspaced. Protection area of coverage is determined by 8.5.2.1.1.
11. Identify all areas with Obstructed Construction on the plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/25/2004 | | 6/25/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/25/2004 | | DONE |
|
|
|
|
Telephone call | | | 6/25/2004 | | DONE |
|
|
|
permit ready and fee due
|
Telephone call | | | 6/18/2004 | | DONE |
|
|
|
Designer: Jeff Pacham indicated that changes are being made to the plans and he has requrested to hold them for changes, prior to reviewing.
|
Application received | | | 6/15/2004 | | |
|
|
|
|
Inspection Record Card- Fire | 11/30/2004 | | | | |
|
|
|
|
Plan assigned to (Bill) | 5/10/2005 | | | | |
Bill Alexander
|
|
|
|