INSP-Final Inspection | 9/2/2004 | 9/3/2004 | 9/3/2004 | A | PASS |
Troy Cobbley
|
|
|
fire sprinklers finaled 9/3/2004 10:23:42 AM
|
DOC - Permit Finaled | 9/3/2004 | 9/3/2004 | 9/3/2004 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 9/3/2004 10:23:46 AM
|
INSP-Conference | 8/24/2004 | 8/24/2004 | 8/24/2004 | P | DONE |
Troy Cobbley
|
|
|
The store owners want to install a sidewall head instead of a upright in the entry canopy. I went over sidewall requirements with him and them we discussed life safety notes and requirements especially for the doors and hardware at the entrance. 8/24/2004 3:55:33 PM
|
INSP-Sprinkler Rough-in | 7/30/2004 | 8/2/2004 | 8/2/2004 | A | PART |
Rick Jackson
|
|
|
Glen; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Okay to cover main entry area - the SSU was replaced with a SSP in thecanopy as the SSU would be obstructed 8/2/2004 10:42:41 AM
|
Plan assigned to (Bill) | 7/6/2004 | | 7/15/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 7/12/2004 | | 7/15/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2004 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/15/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 7/15/2004 | | 7/15/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/15/2004 | | DONE |
|
|
|
Spoke with Brodie and told him that permit is ready & fees///7/15/04 9:50am BAM
|
(F) Reprint permit | | | 7/15/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/12/2004 | | |
|
|
|
|
Sprinkler Plan Check | 7/7/2004 | | 7/9/2004 | | FAIL |
Bill Alexander
|
|
|
|
Miscellaneous action | | | 7/9/2004 | | DONE |
|
|
|
Took plans and documents to permit desk for calling and returning
|
Telephone call | | | 7/9/2004 | | DONE |
|
|
|
PLANS FAILED REVIEW
|
Application received | | | 7/6/2004 | | |
|
|
|
|