INSP-Final Inspection | 9/22/2006 | 9/22/2006 | 9/22/2006 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
FIR-Aging Inspection | 11/21/2005 | 11/21/2005 | 11/21/2005 | | CANC |
Troy Cobbley
|
|
|
|
Plan resubmittals received | | | 7/15/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 7/15/2005 | | PASS |
|
|
|
Plan Modification. Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/15/2005 | | DONE |
|
|
|
|
Issue and Print Permit | | | 7/15/2005 | | DONE |
|
|
|
|
FIR-Aging Inspection | 6/24/2005 | 6/24/2005 | 6/28/2005 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|
Issue permit | | | 3/25/2005 | | |
|
|
|
|
Telephone call | | | 3/24/2005 | | DONE |
|
|
|
Received a call from Bob Brewton (Idaho State Elevator Inspectors) stating that the smoke detector in the top of the shaft is NOT a requirement and it should be deleted. Also the controller location may warrant smoke and heat for recall/shunt trip pending sprinkler plans. I phoned Jason Minnick (AEI) and informed him of the above. I marked up the plan (has been issued, he just has not picked them up yet.) and informed him that a resubmittal may be required if the PDS Fire Inspector deems necessary. An updated building map shall be provided regardless.
|
Plan assigned to (Mary) | 7/19/2004 | | 3/23/2005 | | DONE |
|
|
|
|
Alarm Plan Check | | | 3/23/2005 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/23/2005 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/23/2005 | | 3/23/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/23/2005 | | DONE |
|
|
|
tlk to jason minnick ###-#### that permit is ready to be picked up
|
Plan resubmittals received | | | 3/22/2005 | | |
|
|
|
|
Alarm Plan Check | | | 7/20/2004 | | FAIL |
|
|
|
Resubmittal Required. Faxed comments to Jason Minnick 7/20.
|
Application received | | | 7/19/2004 | | |
|
|
|
|