Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR04-00431
StatusFinaled
Name NORTHWEST SALES COMPANY
Site Address 601 N PHILLIPPI ST
Project Namealm - Stein Distributing
Customer Number 
ePlanReview 
Description
To add monitoring of hi/lo air, valves and flow on a new dry sprinkler system. The existing required sprinkler monitoring system includes HVAC shutdown.

The associated sprinkler permit (FIR 03-00779) is to fulfill letter agreement on file to fire sprinkler the entire building, for the allowance for non separation of the offices to the warehouse area and allow for certificate of occupancy and completion in the building permit this permit is attached. Work scope entails extending the wet into all heated areas and extending an existing dry system and adding a new dry system. Also includes the relocation of the existing compressor to the new dry system and installing a new compressor to the existing system (for the added system capacity). The fire sprinkler system work shall comply with IFC 2000, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD03-00657. STEIN DISTRIBUTING CO., INC.)

The associated building permit (BLD 03-00657) is to remodel an existing 1,768 sq.ft. two story office area within the warehouse and expand office area to 1,768 sq.ft. for a total office area of 3536 sq ft, and to remodel front of building per approved plans and attached engineering and CZC03-00025. Work will include, separating the office area from the warehouse with two hour fire barrier walls, this includes new walls around new portion and upgrading walls and openings around existing office area, construction of vertical exit enclosure from second floor area, remove and rebuild stairs on lower level access to warehouse area, remodel two restrooms to make fully accessible, new exterior siding at office area, new landing, fire sprinklering office area, new lighting system and new HVAC System. This building is partially sprinklered for High piled storage letter on file to sprinkler building by 2006. (pc#158-03) rmh PLAN MODIFICATION 8/18/03. PLANS ARE BEING RESUBMITTED WITH THE BUILIDNG FULLY FIRE SPRINKLERD, THIS WILL ALLOW FOR NON SEPARATION OF THE OFFICE AREA TO THE WAREHOUSE. NO SEPARATIONS ARE REQUIRED, NO CERTIFICATE OF COMPLETION OR CERTIFICATE OF OCCUPANCY WILL BE GRANTED UNTIL SPRINKLER SYSTEM IS INSTALLED AND APPROVED BY FIRE DEPARTMENT. THIS WILL FULL FILL REQUIREMENT OF LETTER ON FILE TO SPRINKLER THE ENTIRE BUILDING. (8/18/03 RMH)- (STEIN DISTRIBUTING CO., INC.)

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Alarm Testing7/26/20047/26/20047/26/2004PPASS
DetailsTroy Cobbley
Fire alarm finaled 7/26/2004 2:55:03 PM
DOC - Permit Finaled7/26/20047/26/20047/26/2004PPASS
DetailsTroy Cobbley
Finaled by inspector at 7/26/2004 2:55:07 PM
Application received  7/23/2004  
Plan assigned to (Mary)7/23/2004 7/23/2004 DONE
Alarm Plan Check  7/23/2004 PASS
Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  7/23/2004 DONE
Permit Ready to Issue  7/23/2004 DONE
Inspection Record Card- Fire7/23/2004 7/23/2004 DONE
Telephone call  7/23/2004 DONE
Spoke with Dave and told him that permit is ready & fees///7/23/04 3:13pm BAM
Issue and Print Permit  7/23/2004 DONE