To upgrade St Al's third floor, south tower, area 311 for code compliance on smoke detector locations (patient rooms and corridors) and chime/strobes in all common and public areas. The required manual fire alarm system includes sprinkler monitoring, elevator recall/shutdown, HVAC shutdown, fire/smoke damper control, door release and notification throughout.

The associated building permit (BLD 04-01245) is to perform selective demolition between two -existing nurse stations and a Soiled Utility room to create one open Nurse's Station. Work includes construction of non-combustible, fire-resistive walls at closet reduced in size and at end of new work counter area; install new accessible service & work cabinetry, suspended ceiling & solid ceiling areas; sprinkler, electrical & mechanical modifications, all per the approved plans, red0line notes and attached plan review comments of all reviewing agencies. PC04-365/drs SARMC - ORTHOPAEDIC JOINT CAMPNURSE STATION REMODEL)(3RD FLOOR SOUTH TOWER) This building is fully sprinklered based on occupancy use. A "Letter of Compliance" is required for this project.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/5/200410/6/200410/6/2004PPASS
DetailsTroy Cobbley
Fire life safety finaled 10/6/2004 2:00:58 PM
INSP-Final Inspection10/6/200410/6/200410/6/2004PPASS
DetailsTroy Cobbley
fire alarm finaled
DOC - Permit Finaled10/6/200410/6/200410/6/2004PPASS
DetailsTroy Cobbley
Finaled by inspector at 10/6/2004 2:00:41 PM
INSP-Final Inspection9/30/200410/1/200410/1/2004PFAIL
DetailsTroy Cobbley
Room 317 no longer exists, its now a therapy room. Change description on fire alarm panel.
Provide a visual device in the short corridor on the south side of the nurses station 9/1/2004 3:15:59 PM
INSP-Alarm Testing9/30/200410/1/20049/30/2004PDONE
DetailsTroy Cobbley
thad; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
Miscellaneous action  9/22/2004 DONE
Phone conversation with Nick at Synergy, comment #6 states that the signal shall be temporal. Per NFPA72 6.8.4.1 (commentary in handbook) "...it may be impractical or undesirable to change an existing evacuation signal that is already recognized by occupants and approved by the AHJ." Therefore, the notification appliances that are installed for this permit may be programmed to "signal" to match the existing.
Issue and Print Permit  8/30/2004 DONE
Alarm Plan Check  8/27/2004 PASS
Approved pending field inspection of fire alarm permit comments.
PLANS/APPL TAKEN TO FRONT DESK  8/27/2004 DONE
Permit Ready to Issue  8/27/2004 DONE
Inspection Record Card- Fire8/27/2004 8/27/2004 DONE
Inspection Record Card- Fire8/27/2004 8/27/2004 DONE
Telephone call  8/27/2004 DONE
Left message for Kurt that permit is ready & fees///8/27/04 1:45pm BAM
Plan assigned to (Mary)8/12/2004 8/27/2004 DONE
Plan resubmittals received  8/26/2004 DONE
Received a copy of the fuel agreement.
Plan resubmittals received  8/19/2004 DONE
Received a fax copy of a revised matrix.
Plan resubmittals received  8/17/2004 DONE
Received a fax copy of the generator information.
Telephone call  8/16/2004 DONE
Request to Nick (Synergy) to send revised matrix. Also require the generator information and fuel agreement.
Miscellaneous action  8/16/2004 DONE
Received a fax copy of a revised matrix. Called Nick, general smoke detecotrs do not recall the elevator, he will send a new one.
Plan resubmittals received  8/16/2004 DONE
Received a fax copy of a revised matrix. Called Nick, general smoke detecotrs do not recall the elevator, he will send a new one.
Application received  8/12/2004