Case Summary | | | 6/3/2005 | | DONE |
|
|
|
|
Case Summary | | | 2/10/2005 | | |
|
|
|
|
INSP-Final Inspection | 12/6/2004 | 12/6/2004 | 12/6/2004 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/6/2004 at 9:06:16 AM. Contact: ###-####.
|
DOC - Permit Finaled | 12/6/2004 | 12/6/2004 | 12/6/2004 | P | PASS |
Rick Jackson
|
|
|
Finaled by inspector at 12/6/2004 4:00:58 PM
|
INSP-Final Inspection | 11/9/2004 | 11/12/2004 | 11/12/2004 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/9/2004 at 12:48:42 PM. Contact: ###-####. Single station alarm in room generate building alarm - not per matrix; speakers operated properly 11/12/2004 10:23:49 AM
|
INSP-Conference | 11/12/2004 | 11/12/2004 | 11/12/2004 | A | PART |
Rick Jackson
|
|
|
Per Sam Rogers the detectors in the space will be a combo smoke/heat detector as this the type of system throughout the exsisting R occupancies; the smoke is local to the room and the heat generates general alarm; this info was passed on the Brian and Chris of Simplex 11/12/2004 10:56:25 AM
|
Plan assigned to (Mary) | 8/26/2004 | | 9/14/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/14/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/14/2004 | | 9/14/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/14/2004 | | |
|
|
|
Spoke with Chris and told him that permit is reasy & fees///9/17/04 9:45am BAS
|
Issue and Print Permit | | | 9/14/2004 | | DONE |
|
|
|
|
Alarm Plan Check | | | 9/13/2004 | | PASS |
|
|
|
Approved pending field inspection of fire alarm permit comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/13/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/10/2004 | | DONE |
|
|
|
Received fax copy of generator information and fuel agreement letter.
|
Telephone call | | | 9/2/2004 | | DONE |
|
|
|
Request to Chris Willis for the generator information and fuel agreement letter.
|
Application received | | | 8/26/2004 | | |
|
|
|
|