INSP-Final Inspection | 2/3/2005 | 2/4/2005 | 2/4/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire sprinkler finaled 2/4/2005 9:56:59 AM
|
DOC - Permit Finaled | 2/4/2005 | 2/4/2005 | 2/4/2005 | A | PASS |
Troy Cobbley
|
|
|
Finaled by inspector at 2/4/2005 9:57:02 AM
|
INSP-Final Inspection | 1/28/2005 | 1/28/2005 | 1/28/2005 | P | FAIL |
Rick Jackson
|
|
|
OH hydro okay; flow switch not working properly - cycles; forward flow of BFP okay 1/28/2005 1:08:42 PM
|
INSP-Supply line flush | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | CANC |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 1/26/2005 at 3:34:50 PM. Contact: ###-####. UG has been hydro'd and flushed 1/27/2005 8:16:38 AM
|
INSP-Sprinkler Rough-in | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | PART |
Rick Jackson
|
|
|
terrry - ###-#### Hydro failed; okay to cover areas identified on plans and resubmittals for beam areas 1/27/2005 10:45:23 AM
|
INSP-Sprinkler Rough-in/Hydro | 1/26/2005 | 1/27/2005 | 1/27/2005 | A | PART |
Rick Jackson
|
|
|
###-#### - terry Note: please call prior to inspection Hydro failed; okay to cover areas identified on plans and resubmittals for beam areas 1/27/2005 10:45:36 AM
|
INSP-Supply line flush | 12/20/2004 | 12/21/2004 | 12/21/2004 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed 12/20/2004 3:21:27 PM
|
INSP-Sprinkler Rough-in/Hydro | 12/20/2004 | 12/21/2004 | 12/21/2004 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed 12/20/2004 3:20:51 PM
|
Issue and Print Permit | | | 12/21/2004 | | DONE |
|
|
|
|
INSP-Conference | 12/16/2004 | 12/16/2004 | 12/16/2004 | P | PART |
Troy Cobbley
|
|
|
Sanctuary piping rough-in is ok 12/16/2004 4:09:40 PM
|
Plan assigned to (Bill) | 12/14/2004 | | 12/16/2004 | | DONE |
Bill Alexander
|
|
|
|
Sprinkler Plan Check | 12/14/2004 | | 12/16/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/16/2004 | | 12/16/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/16/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/16/2004 | | DONE |
|
|
|
tlk to secretary ###-#### that permit and fees are ready to be picked up
|
INSP-Conference | 12/13/2004 | 12/14/2004 | 12/14/2004 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping in the central corridor is ok to cover 12/14/2004 8:34:40 AM
|
Plan resubmittals received | | | 12/14/2004 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 12/9/2004 | 12/10/2004 | 12/10/2004 | A | PART |
Troy Cobbley
|
|
|
Combustible concealed spaces as discussed down the main corridor and for the beams over the classrooms need to be filled with non-combustible insulation or add upright sprinklers 12/10/2004 12:10:05 PM
|
Telephone call | | | 12/9/2004 | | DONE |
|
|
|
tlk to jeff packaham that his permit and fees are ready to picked up
|
Issue permit | | | 12/9/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 12/2/2004 | | 12/9/2004 | | PASS |
Bill Alexander
|
|
|
Installation changes/modifications and corrections.
|
Plan assigned to (Bill) | 12/2/2004 | | 12/9/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/9/2004 | | 12/9/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/9/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 12/2/2004 | | |
Bill Alexander
|
|
|
|
INSP-Sprinkler Rough-in | 11/12/2004 | 11/15/2004 | 11/15/2004 | A | CANC |
Troy Cobbley
|
|
|
Per Russ with treasure valley fire 11/15/2004 8:06:08 AM
|
INSP-Sprinkler Rough-in/Hydro | 11/2/2004 | 11/3/2004 | 11/3/2004 | P | PART |
Troy Cobbley
|
|
|
Overhead sprinkler piping in the remodeled classrooms and the new wing is ok. A second inspection will be needed for piping to pendants. There a pipe sizes installed that do not match approved plans as well as pendants installed in areas not shown to have ceilings. Resubmit plans to city of boise for approval showing ceilings and actual pipe sizes 11/3/2004 4:14:13 PM
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2004 | 10/4/2004 | 10/4/2004 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler supply stub-in is ok to bury 10/4/2004 4:34:42 PM
|
Issue permit | | | 9/28/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/17/2004 | | 9/27/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/17/2004 | | 9/27/2004 | | PASS |
Bill Alexander
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/27/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/27/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/27/2004 | | 9/27/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/27/2004 | | DONE |
|
|
|
Left Jeff a message that permit is ready & fees///9/27/04 4:05pm BAS
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2004 | 9/22/2004 | 9/22/2004 | P | PART |
Troy Cobbley
|
|
|
Inspection was just for the underground. Piping is ok to bury from the tap to the curbing just outside of the building. 9/22/2004 4:11:44 PM
|
Plan resubmittals received | | | 9/17/2004 | | DONE |
Bill Alexander
|
|
|
|
Permit Ready to Issue | | | 9/16/2004 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/16/2004 | | 9/16/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/16/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Issue and Print Permit | | | 9/16/2004 | | DONE |
|
|
|
|
Plan assigned to (Bill) | 9/7/2004 | | 9/15/2004 | | DONE |
|
|
|
|
Sprinkler Plan Check | 9/7/2004 | | 9/15/2004 | | PART |
Bill Alexander
|
|
|
Approved Underground Supply Only.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2004 | | DONE |
|
|
|
|
Application received | | | 9/7/2004 | | |
|
|
|
|